MHH626773 Renewable Power Integration Coursework

Important notes:

  • This coursework is composed of Two-Parts that run-in succession. The two parts are correlated. Part I runs from week 1 to week 6 and Part II runs from week 7 to week 12.
  • Coursework report submission date: 16:00 pm Week 13 Wednesday 21st December 2022.
  • One electronic coursework report including Part I and Part II to be submitted on the due date.
  • Online submission link will be available a few days before the due date.
  • Concise presentation is encouraged. Coursework report should NOT be longer than 4000 words (excluding tables, figures, data appendix and references). There is no lower limit of word count.
  • Ensure the title of coursework, date, your name and matriculation number are included on the front cover.
  • Coursework weight is 30% of total module mark. Coursework marks will be distributed as follows:

Part I is worth 50% of coursework mark Part II is worth 50% of coursework mark

The overall mark allocation of this coursework is: –       Presentation, structure and readability  20%
–       Technical content and relevance50%
–       Relevant discussion and conclusions20%
–       Proper use of background reading and references10%
  • Plagiarism

Please note the following School statement on Plagiarism: “The deliberate and substantial unacknowledged incorporation in your submission of material

derived from work (published or unpublished) of another is prohibited. In such cases the work submitted is classified as illegal and will result in further action being taken by the University which may include recording a failure.

Part I

Impact of Distributed Generation on the Performance Indices of Power System

  • Introduction

The Figure below shows a part of a distribution system with an embedded generator (EG).

Fig. 1 Simple distribution network with embedded generation (EG).

Initial Support:
  • A Simulink model file named ‘Dist_Network_with_EG’ in which you will build the network model can be found on GCU Learn under “Assignment and test” section.
    1. The network information and load data are provided in the appendix (supportive tips and instructions), please read it carefully.
    • A video guidance is provided on GCULearn under “Assignment and test” section. It is a guidance of how to establish the first model and obtain the first set of result.

(II).     Tasks to do:

Starting with the file ‘Dist_Network_with_EG’ and using the guidance in the appendix (supportive tips and instructions), build a Simulink model representing the considered distribution network. Then work out Tasks A and B.

Task A

Consider the following four cases and accomplish the sub-tasks listed below:

Case I The system is supplying its maximum loads (initial values of load 1, load 2 and load 3 in the appendix) and the distributed generator is not producing any power.

Case II The system is supplying its minimum load where all loads are 10% of its maximum values (active and reactive powers). The distributed generator is not producing any power.

Case III The system is supplying its maximum load and the distributed generator is producing 30 MW active power.

Case IV The system is supplying its maximum load for Load 1, whereas Load 2 and Load 3 re 10% of its maximum values. The distributed generator is producing 30MW active power.

A-1.     Using Power GUI Load Flow tool (open PowerGUI block àTools àLoad Flow), calculate the voltages at all busbars for each of the 4 cases.

  • For the initial values, please follow the appendix of this assignment paper.
  • The values used in the video guidance are illustrative and might not be the correct one.

[5 marks]

A-2.     Considering that ±5% variation from nominal voltage is acceptable for every busbar, find the appropriate tap position of 132/33 kV transformer for each of the 4 cases.

  • Assume the available tapping positions are -5% to +5%.
  • All eligible tapping positions are required for each case. The selected tapping positions for different cases can be different.

[5 marks]

A-3.     Briefly explain the EG’s impact to the voltage profile at each bus bar based on the results obtained in Tasks A-1 and A-2.

[5 marks]

A-4.     Using “report” in Load flow tool, obtain the following profiles for each of the 4 cases in Task A-1 (all tapping positions at 0%):

  1. the total production and consumption of active power in the network
    1. the total production and consumption of reactive power in the network

[5 marks]

A-5.     Critically analyze the results of Task A – 4 and briefly explain how the losses and voltages are influenced by the DG and loads.

Task B

[5 marks]

B-1.     Based on Task A – Case I, change the EG power from 0 to 60 MW (using steps of 5MW and initial settings) and plot the following curves:

  • Total active power losses Vs. the EG power generation
    • The absolute value of active power carried by the 33kV feeder Vs. the EG power generation.

[5, 5 marks]

Hint:

  • To plot the curves, any systematic approach can be used.
  • Optional approaches typically include (not limited to):
  1. collect the data in matlab manually and use “plot” function in matlab;
  • collect the data in matlab and plot the graph with other software, e.g. Excel;
  • collect the data in matlab and plot the curve manually;
  • write a matlab code to generate the graph automatically;
  • Reasonable evidence must be provided to show how the results are obtained.

E.g. the scripts for matlab coding approach, data for manual/Excel plotting approach, etc.

B-2.     Accomplish the following tasks:

  • Define the hosting capacity of EG.
  • List 3 possible performance indices that can determine hosting capacity.
    • Using active power losses as the performance index, determine the hosting capacity against active power losses in this network. Briefly justify your decision.

[5 marks] B-3.  Propose at least two methods to upgrade the hosting capacity for this network. Explain how they would work according to the previous analysis in Tasks A and B. (Note: Be specific and direct in your answer. Vague or inaccurate information will impact your mark.)

[10 marks]

Appendix – Supportive Tips and Instructions:

To build the Simulink model:

  • Open the ‘Dist_Network_with_EG’.
  • Open Simulink library browser (view à library browser) or press CTRL+SHIFT+L.
  • Search the library browser for the following blocks (once you find a block, drag-and- drop in the model):
    • Three-phase source
    • Three-phase transformer (two windings)
    • Three-phase parallel RLC load
    • Three-phase PI section line
    • Simplified synchronous machine (pu units)
    • Load Flow Bus
  • Connect the blocks to build the network of Fig 1. Connect the block ‘busbar’ at the connection point of any two electrical nodes of the network (as in Fig. 1). Rename the busbars in your model as in Fig. 1.
  • Double click each block to configure its parameters.
  • Three-phase source:
  • In ‘block parameters’ window, configure this block as a grounded-star (Yg) source, Vrms = 132kV, phase angle of phase A = 0°, frequency = 50Hz, base voltage

= 132kV, X/R ratio = 5, short-circuit level at base voltage = 1500MVA.

  • Open ‘Load Flow’ tap and change generator type (busbar type) to ‘swing’. This makes sure the busbar connected to the source is identified as a slack bus.
  • Three-phase transformer:
  • In ‘configuration’ tab choose grounded-star (Yg) connection for primary and secondary windings. Configure the transformer as three single-phase transformers.
  • In ‘parameters’ tab set ‘units’ to ‘pu’ and define nominal power Pn = 50MVA, frequency = 50 Hz, Rm = 1500 p.u., Lm = 100 p.u..
  • Primary winding (winding 1) parameters: V1 = 132kV, R1 = 0.0032pu, L1 = 0.08 p.u.
  • Secondary winding (winding 2) parameters: V2 = 33kV, R2 = 0.0032pu, L2 = 0.08 p.u.
  • Three-phase parallel RLC load (Load 1):
  • In ‘Parameters’ tab configure the load as a grounded-star (Yg). Nominal voltage and frequency are 33kV and 50 Hz, respectively. Load 1 is 20 MW active power and 4 MVAr inductive reactive power.
  • In ‘Load Flow’ tab, change ‘Load type’ to ‘constant PQ’ such that the loading remains near-constant regardless of operational conditions (e.g. voltage variations).
  • Three-phase parallel RLC load (Load 2):

–      Repeat the same configuration as for Load 1. Load 2 is 12 MW active power and 4 MVAr inductive reactive power.

  • Three-phase parallel RLC load (Load 3):

–      Repeat the same configuration as for Load 1. Load 3 is 10 MW active power and 3 MVAr inductive reactive power.

  • Three-phase PI section Line 1:
  • Specify feeder length (line length) as 7 km. Frequency = 50Hz.
  • Positive- and zero- sequence resistances (r1, ro) = 0.2Ω/km and 0.413Ω/km, respectively.
  • Positive- and zero- sequence Inductances (L1, Lo) = 1mH/km and 5.32mH/km, respectively.
  • Positive- and zero- sequence capacitances (c1, co) = 13.3pF/km and 50.1pF/km, respectively.
  • Three-phase PI section Line 2:
  • Specify feeder length (line length) as 3 km. Frequency = 50Hz.
  • Same parameter as for Line 1.
  • Simplified synchronous machine (pu units)
  • In ‘Configuration’ tab, set connection type to ‘3-wire Y’ and set ‘mechanical input’ to ‘mechanical power Pm’.
  • In ‘Parameters’ tab, set nominal power Pn = 30MW, nominal voltage Vn = 33kV, nominal frequency fn = 50Hz.
  • Set inertia constant (H) to H = 3s, number of pole pairs p = 20.
  • Set armature resistance R = 0.04pu, armature reactance X = 0.5pu
  • In ‘Load Flow’ tab, set generator type to ‘PV’, which defines the B33_2 busbar as a generator bus in the load flow analysis. Set ‘Active Power Generation’ to P = 0 initially to prepare the model for running Case I. When running load flow analysis for other cases, set ‘Active Power Generation’ in ‘Load Flow’ tab to the relevant value.
  • Set maximum and minimum reactive power Qmax = 1 MVar and Qmin = – 1 MVar. Note this reactive power support range from the EG is limited to reflect real situations where renewable technology is normally unable to provide as much reactive power support to the network as conventional power plants.
  • In your model, connect two constant blocks (obtain them by drag-and-drop from library browser) to the inputs Pm and E of the ‘simplified synchronous machine’ block to account for the mechanical input power and generator excitation.
  • Load Flow Bus:
  • Connect a ‘Load Flow Bus’ to one line (any phase) near each busbar in the model. This block configures Simulink to include the busbar to which it is connected in the load flow analysis.
  • As there exists three busbars in this network, three Load Flow Bus blocks will have to be connected to the network in the model.
  • In ‘Parameters’ tab, set ‘connectors’ to single. This implies connection of the block to a single line of the three phase lines, which is sufficient to fetch the busbar voltage magnitude in a balanced three phase system (such as the considered network). Note that in unbalanced three phase networks, more than one line need to be connected to the block as you may see in other options in the drop menu (the block will have more than one connection port in this case).
  • Set ‘Bus identification’ to the relevant bus name as in Fig. 1
  • Set base voltage as the nominal voltage level at the relevant bus.
  • Set ‘swing bus or PV bus voltage (pu)’ to 1.02 at the B132 busbar and to 1 at B33_1, B33_2 and B33_3 busbars.
  • The voltage at bus B132 is assumed to be held constant at 1.02 pu since this is defined as the slack bus.
  • Note that the Load Flow Bus (the orange box) on each busbar is not a part of the actual power network, rather a block to fetch busbar parameters for load flow analysis and show the voltage of the bus (magnitude and angle)
  • On carrying load flow analysis, change the active power generation of the embedded generator by opening synchronous machine ‘block parameters’ and change the active power generation in the ‘Load Flow’ tab to any value.
  • To carry out load flow analysis, open PowerGUI block àTools àLoad Flow. A new window opens. Before you run load flow, press ‘update’. When the white text line shows “ready!”, press ‘compute’, then ‘apply to model’. You will notice the new pu voltage values (magnitude and angle) updated beside each Load Flow Bus.
  • Each time after you change block parameters in the Simulink model subject to cases I- IV, you must click “Update”, “Compute” and then “Apply to Model” in the Power GUI Load Flow tool window to view (and reflect) the updated network status on each Load Flow Bus.
  • As an example: to update the model from Case I to Case II, you need to change load 2 to 10% of its maximum value. One way of doing so, open the block parameter of Load 2 and multiply both active and reactive power numbers by 0.1. Now go to the PowerGUI Load Flow Tool window and click “Update”, “Compute” and then “Apply to Model”. Now the load flow results represent Case II.
  • To generate the “report”, simply click “report” button in the PowerGUI Load Flow Tool window and choose to save the report in Excel file (preferable). Save each excel file you generate in a separate name to avoid overwriting old reports. In the excel file you can find data on total power generation and consumption as well as power flows from and to each bus bar (adjust columns width to view the data comfortably in the Excel sheet).
  • Don’t forget to reset Load 2 to the maximum value before you run load flow for Case II or Case III.
  • At any load flow run, if the voltage of any busbar is outside the ±5%, the tolerance, tap position has to be changed until all busbar voltages fall within the tolerance. Only then you can log relevant results to your CW report.
  • In order to adjust the transformer tap position: Open the block parameter dialogue of the transformer and use an appropriate multiplier for the winding 2 phase-to-phase voltage (i.e.: use 1.01 for tap changer position at +1% and use multiplier 0.98 for tap changer position at -2%).
  • It may not be always possible to find a single tap position that satisfies the voltage tolerance for all the cases. If you ever meet such a condition, note it in your CW report.

End of Part I

Part II

Modelling and Operation of The Renewable Embedded Generation Plant

1.   Introduction

In this exercise, we will zoom in to the EG of Part I of this CW to see some of the possible technologies used. You will learn about the components and operation of a renewable power plant (RPP) using Matlab coding and Simulink models. The RPP consists of a combination of 200kW solar farm and a 9MW wind farm built of six 1.5MW doubly-fed induction generator wind turbines (DFIG-WTs).

The specific purposes are:

  • To understand the relation between voltage and current of a photovoltaic solar panel under various operating conditions.
  • To understand the relation between wind turbine performance coefficient (cp) and tip- speed ratio (λ) at different values of pitch angle (β).
  • To build the power circuit in a Simulink model of a 1.5MW DFIG wind turbine (being one of six WTs in a 9MW DFIG wind farm) and simulate it at steady state conditions and familiarize with turbine components.
  • Develop theoretical background on DFIG operation using simulation runs at various steady state operating points and parameter values.
  • Investigation of DFIG operation at different wind speeds:
  • Identification and exploration of different control regions within the power curve.
  • Exploration of power and rotor speed relationships in DFIG.
  • Exploration of stator and rotor currents and voltages at different slip values (using simulation runs).

2.   Tasks

Task a

Developing solar panel I-V and P-V curves at different temperature and irradiance conditions                                                                        [Total: 20 marks]

You are required to read Appendix A carefully and then:

  1. Plot the I-V curve of equation (3) of Appendix A if the PV cell has the following characteristics: Io= 0.1 nA , IL = 9.5 A [5 marks]
  2. Plot the I-V and P-V curves of a solar panel composed of 72 series-connected cells of the type detailed in i) at 25 °C and 1000W/m2 irradiance.                                                                                                [5 marks]
  1. Repeat your plot in ii) for irradiance levels G = 800 W/m2, 650 W/m2, and 350 W/m2.                                                                                                       [5 marks]
  2. Find the voltage and current of the panel at maximum power point under each irradiance level.                                                                                                         [2 marks]
  3. Critically analyze your graphs as to how the change of irradiance affects the operation and output of the solar panel.                                                                                                        [3 marks]

Task b

Developing cp – λ curves at different values of pitch angle (β)                 [Total: 10 marks]

In this task, you are required to write the necessary Matlab commands in an m-file to plot (cp – λ) curve for different values of pitch angle (β) using equations (10) and (11) of Appendix B. Use the following values for constants c1 through c6:

c1 = 0.518, c2 = 116, c3 = 0.4, c4 =5, c5 = 21, c6 = 0.0069

The considered values of pitch angle β are: 0°, 2°, 4°, 6°, 8°, 10°.                                                                                                                             [6 marks] For the (cp – λ) curve you generate for β = 0°, obtain values of λopt and cp_max and plot equation

  • of Appendix B to see how the mechanical power relates to turbine rotor speed. [2 marks]
Indicative steps (this is an example as there is more than one way to generate these plots, so feel free to follow different reasoning to build your graphs if you wish):
  • Define a vector of λ values from 0 to 16 with 0.01 resolution (i.e. 1600 points)
    • Code equation (11) of Appendix B
    • Code equation (10) of Appendix B for first value of β (i.e. β = 0°)
    • Plot cp(λ,β) against λ vector.
    • Change value of β.
    • Plot the new cp(λ,β) curve against λ vector on the same figure (use hold on or hold all command)
    • After plotting all curves for all values of β, save your figure and extract it into your report where figure title, axes and legends are well indicated.
    • Use “data cursor” tool in the figure window to obtain values of λopt and cp_max from each (cp – λ) curve in your figure.
    • Use λopt and cp_max values at β = 0° to plot equation (9) of Appendix B into a new figure or a new subplot of the same figure. Plot title, axes and legends are well indicated. Assume WT rotor diameter to be D = 120m; and rotor speed range under MPPT (i.e. while λ = λopt ) is from 5rpm to 17.5rpm.

Critically analyze your graphs as to how the change of pitch angle affects the performance coefficient (efficiency) of the wind turbine and its mechanical output.                                                                                                                                 [2 marks]

Task c

Build a grid-connected DFIG-WT Simulink model:                          [Total: 20 marks]

Fig. 2 Structure of DFIG-WT

Open the file named “CW_DFIG_WT_Model.slx” in Matlab. Familiarize yourself with the model and included descriptions. You will notice the circuit of Fig 2 is modeled as separate blocks of different color codes. The color codes separate between different components of the model (e.g. power circuit components, controllers … etc.) as explained below:

Blue: Electric power circuit components such as generator, converters, etc …

Orange: Control blocks; pitch control, rotor side converter (RSC) control, grid side converter (GSC) control … etc.

Red: “go to” tags or measurements blocks that allow sending signals from specified blocks (wireless transmitter for control signals)

Green: “from” tags that allow the reception of signals specified by the “go to” tags (wireless receiver for control signals)

Grey: Scopes

Yellow: Customizable control block.

  1. Complete building the grid-connected DFIG-WT Simulink model. Connect all the power circuit blocks you find inside the “block inventory” in the considered model in the proper manner (Use Fig. 2 as a reference and observe the model has three phase blocks as opposed to the single line diagram of Fig 1). Do not attempt to change or move the busbars from where they are originally. Connect the blocks accordingly between relevant busbars. Make sure you have consistent phase sequence (a, b, c) in all connections. Include a snapshot of your connected model in the final report.
[2 marks]

Delete the “block inventory” when your model is ready, run the simulation and make sure your model runs correctly.

  • Explain briefly (in no more than 3 lines) the function of each Blue block in the DFIG- WT with reference to this Simulink model (Up to the PCC).                                                                                                             [3 marks]
  • Wind speed step change: In the block “wind” set the input selection block to 2 and run the simulation. The wind speed has a negative step change from 10.5 m/s to 8m/s at t=1s.

Monitor scopes including pitch angle, rotor current, and RSC and GSC Active and reactive power flows. Explain why the DFIG exhibits such behaviour (e.g. rotor currents and power flows) for a step change in wind speed. [Hint: you are not required to export plots to your report]

[5 marks]
  • Ramp wind speed change: In the block “Wind” select the Ramp Wind option by setting the input selection to 3 and run the simulation.
    • Discuss briefly the main differences in WT operation between the wind speed ramp with a slope of -1 and a slope of 2 (you may support your discussion with plots of rotor speed and pitch angle only). [3 marks]
    • Change WT inertia to H=3.7s and check WT behavior with higher inertia at slope

2. Export plots for rotor speed and current and pitch angle only for the two values of H and comment on the plots.                                                                                                               [2 marks]

[Hint: to change WT inertia: right click anywhere in the model à model properties à callbacks tab à InitFcn*. Then change the value of (H)]

  • Random wind speed: Return WT inertia constant to (H = 2.04). Change simulation time to 10s. In the block “wind”, select the “random wind source” by setting the input selection at 4 and run the simulation.
    • Why the rotor speed change is significantly slower and smoother than the wind speed change? [1 marks]
    • In the model, change the constant input “pu speed reference” of the “pitch control” block from 1.21 to 1.13. Run the simulation and export the plot of the pitch angle and DFIG-WT stator and rotor power profiles only before and after changing the pu speed reference.                                                                                                  [2 marks]
    • Comment on the results shown in exported plots. [2 marks]

End of Tasks

Appendix A

The PV cell is a P-N junction similar to a diode. The diode V-I equation gives an expression for the current through a diode as a function of voltage. This equation for an ideal diode is expressed as:

𝑞𝑉

𝐼 =  𝐼𝑜 (𝑒𝑘𝑇  − 1)                                                                                             (1)

where:

I = the net current flowing through the diode;

Io = “dark saturation current”, the diode leakage current density in the absence of light; V = applied voltage across the terminals of the diode;

q = absolute value of electron charge; k = Boltzmann’s constant; and

T = absolute temperature (K).

In darkness (in the absence of light), the solar cell acts similar to a diode and its operation in darkness will be according to (2). Note that (2) is the same as (1) with a reversed sign to reflect the reference current direction of the solar cell being out of the positive voltage terminal of the cell, unlike the reference current direction in a diode which is considered into the positive terminal of the diode.

𝑞𝑉

𝐼 =  𝐼𝑜 (1 − 𝑒𝑘𝑇)                                                                                          (2)

The IV curve of a solar cell under light is the superposition of the IV curve of the solar cell diode in the dark and the light-generated current (IL). The light has the effect of shifting the IV curve upward where power can be extracted from the solar cell. So, illuminating a cell adds to the normal “dark” currents in the diode so that the solar cell I-V equation becomes:

(𝑞𝑉)

𝐼 = 𝐼𝐿 − 𝐼𝑜 (𝑒 𝑘𝑇

− 1)                                                      (3)

Irradiance level (G) can be considered in the cell I-V relation of (3) as shown in (4), where Gr is the reference level of Irradiance being 1000W/m2.

𝐼 = (𝐼𝐿 ×

𝐺

𝐺𝑟

(𝑞𝑉)

) − 𝐼𝑜  (𝑒 𝑘𝑇

− 1)                                             (4)

Appendix B

As you know from lectures, the power captured from wind by a wind turbine is defined as:

3 Pm = ½ ρAvw cp(λ,β)(5)

Where ρ is air density in kg/m3, A = πR2 is rotor blades swept area in m2, and vw is wind speed in m/s, β is pitch angle, and cp being the performance coefficient (aerodynamic efficiency) of the WT .

Tip-speed ratio (λ) is defined as the ratio of blade tip speed to incoming wind speed:

𝑣𝑡𝑖𝑝          𝜔𝑟𝑅 𝜆 =            = 𝑣w             𝑣w(6)

Where ωr is rotor speed in rad/s, R is radius of rotation in m. As can be seen from (6), a wind turbine operates at a constant tip-speed ratio if the rotor speed is controlled to change proportionally with wind speed (i.e. the ratio between blade tip speed and wind speed remains constant). Normally, the controller ensures that the wind turbine operates at the optimal value λopt which corresponds to cp peak value cp_max on the cp-λ curve. Thus, the wind turbine operates at highest efficiency at every wind speed.

Rearranging (6);

𝜔𝑟𝑅 𝑣𝑤 =     𝜆(7)

Substituting (7) in (5) results in (8).

P = 0.5 πR5 ρ 𝜔 3 c (λ, β) m                                     𝑟     p 𝜆3(8)

It can be observed from (8) that at constant values of λ and β, WT input mechanical power Pm

𝑟  

(and also electrical output power Pe) is proportional to 𝜔3. At the optimal values λopt and cp_max,

equation (8) reduces to (9).

Pm = k𝜔3 𝑟(9)

Where      k = 0.5 πR5 ρ 𝐶𝑝_𝑚𝑎𝑥

(𝜆𝑜𝑝𝑡)3

The values of λopt and cp_max can be obtained from the (cp – λ) curve. The relation between performance coefficient and tip speed ratio (cp – λ) at a certain pitch angle (β) is expressed as follows:

c  (l, b ) = c ( c2   – c b – c  )ec5 / m  + c l p                          1    m      3              4                          6(10)

Where μ is expressed as in (11).

μ =1/ [      1         – 0.035                     λ+0.08β        β3+1](11)

In (10), constants c1 through c6 differ in value from a WT design to another.

Tips and Instructions on Exporting Simulink Plots

There is more than one way you can export neat and clear plots from Simulink scopes. You are free to do it the way you prefer as long as the figures are neat, clear, and readable (and not of a black background!).

One way to export high quality neat waveform from Simulink scopes to your report in a few simple steps is as  follows. This guideline  also (starting from step 2) applies to editing figures/plots generated from Matlab command line.

When you double click the scope and see the waveform in a new window follow these steps: 1- Go to File menu; choose “print to figure” [A new Matlab figure window will open]

  • Save the Matlab figure to your drive: File –> Save as.. [Save the file as a Matlab figure (*.fig) for later edits or retrieval if needed]
  • Go to Edit menu; click “Figure properties” .. [An edit panel will appear below the graph/plot] 4- In the edit panel; change figure colour (bottom left of the panel) from black to white. [You

will notice axes background colour turns to white]

  • Go to Edit menu; choose “Axes properties”…. [A different edit panel will appear below the

graph/plot]

  • Change parameter “Colors” from black to white. [You will notice now all the graph is of white background]
  • On the same panel, you can directly change X and Y axes labels and the limits displayed in your graph by selecting the relevant X or Y Axis tab.
  • Go to “Font” tab to change the font name and size…. [This is an important step to provide

readable font sizes for markers]

  • After finishing edits, save the graph from “File” menu as a “.jpg” or “.tif” image file. 10- Make sure to save your edits on the figure file you saved earlier (*.fig).

The image file can be then exported/copied to your report. Make sure to include proper caption and figure number to your figure in the report.

End of Part II

Order Now

Get expert help for Renewable Power Integration Coursework and many more. 24X7 help, plag-free solution. Order online now!

Universal Assignment (March 3, 2026) MHH626773 Renewable Power Integration Coursework. Retrieved from https://universalassignment.com/mhh626773-renewable-power-integration-coursework/.
"MHH626773 Renewable Power Integration Coursework." Universal Assignment - March 3, 2026, https://universalassignment.com/mhh626773-renewable-power-integration-coursework/
Universal Assignment November 4, 2022 MHH626773 Renewable Power Integration Coursework., viewed March 3, 2026,<https://universalassignment.com/mhh626773-renewable-power-integration-coursework/>
Universal Assignment - MHH626773 Renewable Power Integration Coursework. [Internet]. [Accessed March 3, 2026]. Available from: https://universalassignment.com/mhh626773-renewable-power-integration-coursework/
"MHH626773 Renewable Power Integration Coursework." Universal Assignment - Accessed March 3, 2026. https://universalassignment.com/mhh626773-renewable-power-integration-coursework/
"MHH626773 Renewable Power Integration Coursework." Universal Assignment [Online]. Available: https://universalassignment.com/mhh626773-renewable-power-integration-coursework/. [Accessed: March 3, 2026]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

Assignment Quantitative CASP RCT Checklist

CASP Randomised Controlled Trial Standard Checklist:11 questions to help you make sense of a randomised controlled trial (RCT)Main issues for consideration: Several aspects need to be considered when appraising arandomised controlled trial:Is the basic study design valid for a randomisedcontrolled trial? (Section A)Was the study methodologically sound? (Section B)What are

Read More »

Assignment Qualitative CASP Qualitative Checklist

CASP Checklist: 10 questions to help you make sense of a Qualitative researchHow to use this appraisal tool: Three broad issues need to be considered when appraising a qualitative study:Are the results of the study valid? (Section A)What are the results? (Section B)Will the results help locally? (Section C) The

Read More »

Assignment Topics

PS3002 Assignment TopicsDear studentsPlease choose one of the topics below. Please note that if you are repeating this subject, you cannot choose the same topic that you did previously in this subject.patellar tendinopathyinstability of the lumbar spinehamstring strainperoneal tendinopathyhip – labral tear.hip osteoarthritispatellofemoral instabilityankylosing spondylitisanterior cruciate ligament rupture (conservative management)quadriceps

Read More »

Assessment 2 – Report

Assessment 2 – Report (1200 words, 30%)PurposeTo demonstrate an understanding of the purpose and application of evidence-based dietary advice and guidelinesLearning objectives1.Review and analyse the role and function of macronutrients, micronutrients and functional components of food in maintaining health2.Understand digestion, absorption and metabolism of food in the human body and

Read More »

Assessment 2 – Individual Case Study Analysis Report

Southern Cross Institute,Level 2, 1-3 Fitzwilliam Street, PARRAMATTA NSW 2150 & Level 1, 37 George Street PARRAMATTA NSW 2150Tel: +61 2 9066 6902 Website: www.sci.edu.auTEQSA Provider No: PRV14353 CRICOS Provider No: 04078ªPage 1 of 16HRM201 Human Resources ManagementSemester 1, 2026Assessment 2 – Individual Case Study Analysis ReportSubmission Deadline: This Week,

Read More »

ASSESSMENT 2 BRIEF HPSYSD101 The Evolution of Psychology

HPSYSD101_Assessment 2_20240603 Page 1 of 7ASSESSMENT 2 BRIEFSubject Code and TitleHPSYSD101 The Evolution of PsychologyAssessment TaskAnnotated BibliographyIndividual/GroupIndividualLength2,000 words (+/- 10%)Learning OutcomesThe Subject Learning Outcomes demonstrated by successful completion of the task below include:b) Examine the significant figures, events and ideas present in the history of psychology.c) Identify and relate the

Read More »

Assessment 1 – Individual Case Study Analysis Report

HOS203 Contemporary Accommodation ManagementSemester 1, 2026Assessment 1 – Individual Case Study Analysis Report (10%)Submission Deadline: This Week, at 11:59 pm (Week 4)Overview of this AssignmentFor this assessment, students are required to analyse an assigned case study about hospitality industry relevant regulations and/or operational and accreditation failures of a hospitality organisation.

Read More »

Assessment Brief PBHL1003FOUNDATIONS OF HEALTH AND HEALTH CARE SYSTEMS

Assessment BriefPBHL1003FOUNDATIONS OF HEALTH AND HEALTH CARE SYSTEMSTitleAssessment 2 TypeEssay Due DateWeek 6 Monday 14 April 2025, 11:59pm AEST Length1000 words Weighting60% Academic IntegrityNO AI SubmissionUse Word Document – submit to Blackboard / Assessments Tasks & Submission / Assessment 2 Unit Learning OutcomesThis assessment task maps to the following Unit

Read More »

Assignment 4 – Intersection Upgrades and Interchange Station Design

CIVL5550: Civil Infrastructure DesignAssignment 4 – Intersection Upgrades and Interchange Station DesignDue: This WeekSubmission Instructions:1.Submit a report of approximately 10 pages, covering the following:Part 1: Intersection Upgrade Design•Propose upgrade schemes for two sign-controlled intersections and one signalized intersection•Use SIDRA to evaluate the performance of both the original and upgraded intersections•Use

Read More »

Assessment Brief 1

1 of 14Assessment Brief 1Assessment DetailsUnit Code Title NURS2018 Building Healthy Communities through Impactful PartnershipsAssessment Title A1: Foundations of Community Health Promotions ProjectAssessment Type ProjectDue Date Week 4, Monday, 22nd of September 2025, 11:59pm AESTWeight 40%Length / Duration 1200 wordsIndividual / Group IndividualUnit Learning Outcomes(ULOS)This assessment evaluates your achievement of

Read More »

Assignment 1 – Digital Stopwatch

Assignment 1 – Digital StopwatchThis assessment is an individual assignment. For this assignment, you are going to implement the functionality for a simple stopwatch interface as shown above. The interface itself is already provided as a Logisim file named main.circ . Your assignment must be built using this file as

Read More »

Assessment Background Country Profile

BackgroundCountry ProfileKiribati is an island nation situated in the central Pacific Ocean, consisting of 33 atolls2 and reef islands spread out over an area roughly the size of India (see Figure 1).i Yet, Kiribati is also one of the world’s smallest and most isolated country. A summary of Kiribati’s key

Read More »

Assessment 3: PHAR2001 INTRODUCTORY PHARMACOLOGY

PHAR2001 INTRODUCTORY PHARMACOLOGYAssessment 3: Case StudyASSESSMENT 1 BRIEFAssessment Summary Assessment titleAssessment 3: Case study Due DateThursday Week 6, 17 April at 11:59 Length•The suggested number of words (not a word limit) for the individual questions within the case study is as indicated at the end of each individual question. Weighting50%

Read More »

Assessment Module 1 Healthcare Systems Handout

Module 1Healthcare Systems HandoutGroup AgendasHealth Professionals: You got into health to help people. However, as an owner and operator of a multidisciplinary practice, you need to see many patients to cover the cost of equipment, technology, office and consumables, and pay your staff. The Medicare benefit doesn’t cover the rising

Read More »

Assessment 2 – Case study analysis 

Assessment 2 – Case study analysis  Description  Case study analysis  Value  40%  Length  1000 words  Learning Outcomes  1, 2, 3, 4, 5, 6, 7  Due Date  Sunday Week 9 by 23:59 (ACST)  Task Overview  In this assessment, you will choose ONE case study presenting a patient’s medical history, symptoms, and relevant test

Read More »

Assessment NURS2018: BUILDING HEALTH COMMUNITIES

NURS2018: BUILDING HEALTHCOMMUNITIES THROUGH IMPACTFULPARTNERSHIPSAssessment 1 Template: Foundation of Community Health Promotion projectOverall word count excluding the template wording (63 words) and reference list:Introduction to health issue:The case study, increase breast screening in Muslim women living in Broadmeadows,Melbourne, focuses on addressing the low participation rates in breast cancer screening amongMuslim

Read More »

Assessment EGB272: Traffic and Transport Engineering (2025-s1)

EGB272: Traffic and Transport Engineering (2025-s1)ashish.bhaskar@qut.edu.auPage 1 of 8Assessment 1A (15%) Cover PageIndividual component: 5%Group component: 10%You are expected to submit two separate submissions:Individual Submission (5%): Each student must submit their own individual report. Details of the individual report are provided in Section 3.1, and the marking rubric is in

Read More »

Assessment 3 – Essay: Assessment 3 Essay rubric

Unit: NUR5327 – Management and leadership in healthcare practice – S1 2025 | 27 May 2025Assessment 3 – Essay: Assessment 3 Essay rubricLearning Objective 5:Differentiate drivers forchange and proactively leadhealth professionalresponses to changing anddynamic environmentsFails toidentify aclear plannedchange ordoes not linkit to thestrategic plan.0 to 7 pointsIdentifies aplannedchange, butthe link

Read More »

Assessment 2 – Case study analysis 

Assessment 2 – Case study analysis  Description  Case study analysis  Value  40%  Length  1000 words  Learning Outcomes  1, 2, 3, 4, 5, 6, 7  Due Date  Sunday Week 9 by 23:59 (ACST)  Task Overview  In this assessment, you will choose ONE case study presenting a patient’s medical history, symptoms, and relevant test

Read More »

Assessment 1 PPMP20009 (Leading Lean Projects)

Term 1, 2025PPMP20009 (Leading Lean Projects)1Assessment 1 – DescriptionAssessment title Case study reportAssessment weight 40% of the unit marksReport length 3000 wordsMaximum 8 pages excluding references and appendicesReport format MS Word or PDFSubmission type IndividualSubmission due by Friday, Week 6Assessment objectiveThe purpose of this assessment item is to help you

Read More »

Assignment Maternity – Paramedic Management

Title-Maternity – Paramedic ManagementCase Study – Home Birth Learning outcomes1. Understand the pathophysiology and prehospital management of a specific obstetric condition.2. Develop a management plan for a maternity patient.3. Examine models of care available for maternity patients.4. interpret evidence that supports paramedic care of the maternity patient and neonate.5. Demonstrate

Read More »

Assignment Guidelines for Cabinet Submissions

Guidelines for Cabinet SubmissionsGENERALThe purpose of a Cabinet submission is to obtain Cabinet’s approval for a course of action. Ministers may not have extensive technical knowledge of the subject matter -and may have competing calls on their time. It is, therefore, important that Cabinet submissions are presented in a consistent

Read More »

Assignment Secondary research structure

Dissertation – Secondary Research – Possible Structure and Content GuideA front cover stating: student name, module title, module code, Title of project moduleleader, supervising tutor and word count.Abstract (optional and does not contribute to your word count)This should be an overview of the aim of the critical review, the methodology

Read More »

Assignment E-Business and E-Marketing

Module HandbookFaculty of Business, Computing and DigitalIndustriesSchool of Business(On-campus)E-Business and E-MarketingModule.2025-26􀀀Contents Module Handbook 1Contents 2Module Introduction 3Module Leader Welcome 3Module Guide 5Module Code and Title 5Module Leader Contact Details and Availability 5Module Team Tutors Contact Details and Availability 5Module Teaching 5Module Intended Learning Outcomes 5Summary of Content 6Assessment and Deadlines

Read More »

Assignment II: Computational Fluid Dynamics (CFD) Analysis of

CRICOS Provider 00025B • TEQSA PRV12080 1MECH3780: Computational MechanicsAssignment II: Computational Fluid Dynamics (CFD) Analysis ofGeneralised Cardiovascular Medical DevicesIntroduction:In this assignment, you will develop your CFD capability by analysing a benchmark casefrom a validation study sponsored by the U.S. Food & Drug Administration (FDA) and fundedby the FDA’s Critical Path

Read More »

LCRM301 Researching criminology

LCRM301 Researching criminology Worksheet 1 This worksheet will be disseminated to students in Week 3 and will assist them in the planning and development of the second assessment task: literature review. PART 1: Refining your topic The topic I am interested in is: I am interested in this topic because:

Read More »

ASSESSMENT TASK 2 – COURT APPLICATION

APPENDIX B: ASSESSMENT TASK 2 – COURT APPLICATION (30% OF FINAL MARK)General informationThis Assessment task is worth 30 marks of your final mark.The task is either making (Applicant) or opposing (Respondent) an application before the Supreme Court in your respective state based on a fact scenario, which will be uploaded

Read More »

Can't Find Your Assignment?