Module 3 – Project Task 1.11 – Calculate Quantities
Inclusion
Structural block including to both levels of the structure and including along Grid 18 but not the walls
- $15,401
Rear Entry door to the unit on the ground floor:
Materials:
- $150 door
- $10 hinges
- $35 door handles
Labor:
- $55 per hr
Total:
- $250.00
Floor system between the ground floor and first floor:
- $6,218 as per quote by Chippie Services
Stairs to the from ground to first floor:
- $4,590 as per quote by Concrete constructions
Windows and doors on the first floor = $2,980
- Total doors and materials: $515
- Labor: $165
- TOTAL: $680
- Exterior doors: 1 @ $150
- Interior doors: 4 @ $35 = $140
- Door handles: 4 @ $35 = $175
- Door hinges: 4 @ $10 = $50
- Windows package: 1 @ $2,300 (labor and materials)
- Labor for doors: 3hrs @ $55 = $165
Roof framing system on the first floor
Wall framing for the ground floor of the café as noted above (approx. 5.6 metres.)
Internal and external walls on the first floor:
- $5,248 as per quote
Roof covering system on the first floor:
- $26,876 as per quote
External finishes to the first floor:
- $5,820 as per quote
Internal Lining
- $4,952 as per quote
Internal Fix:
- $1,431 as per quote
Internal Finishes:
- $3,400 as per quote
Electrical:
- $7,520 as per quote
Cabinetry:
- $3,500.25 as per quote
Waterproofing to the terrace:
- $1,110 as per quote by Wet Areas & Tiling
Tiling to the terrace
- $2,325 as per quote by Wet Areas & Tiling
Handrails:
- $1,075 as per quote by Chippie Services
Structural, passive and active fire protection:
- $1000 as per quote
Exclusions:
- Shop fitting to front elevation of the ground floor Café
- Internal walls and fit out to the ground floor café
- Plumbing
- The ground slab for the shop and Café.
- North and south walls to shop 4 adjacent to the café
Identify all materials required for the project
- Internal doors
- External doors
- Toilets
- Urinals
- Basins
- Bath
- Ovens
- Sinks
- Stove cooktops
- Bar
- Cool room
- Floor tiles
- Carpet
- Blockwork
Measure and Calculate quantities of materials required for the project
- 15x internal doors
- 2x external door
- 5x toilets
- 2x urinals
- 5x basins
- 1x bath
- 2x ovens
- 3x sinks
- 2x stove cooktops
- 1x cool room
- 1x bar
- 1m (H) x 0.9m (W) x 2.05m (L)
- Framing material
- 30 l/m bottom floor
- 40 l/m first floor
- Overall 70 l/m
- 70 l/m top plate x2 @ 90x35mm
- 70 l/m bottom plate @ 90x35mm
- 70l/m noggins (reference same as top and bottom plates)
- 116 timber studs (70 / 0.6 = 116) x 5.61m (heights)
Overall 650 l/m
- Plaster/Cement sheeting
- Walls: 64m2 ground floor
- Walls: 71m2 first floor
- Walls overall: 262m2
- Ceiling: 169m2 ground floor
- Ceiling: 169m2 first floor
- Ceiling overall: 338m2
Overall 756m2
- Paint
- 225 litres of paint (3 coats @ 75 litres ea)
- Overall round up to 250 litres
- Floor tiles – bathroom
- Interior: 20m2
- Exterior: 87m2
- Splashbacks
- 12l/m at 600mm high
- Overall 7.2m2
- Carpet – bedrooms
- 32m2 living/stairs
- Balustrade
- 25l/m @ 1.2m high
- Blockwork
- 39l/m = 222 m2
- Tiles to terrace
- 87m2
- Identify and determine labor requirements for the project
Identify and determine quantities required for labor
- Block layer x5
- Carpenter x4
- Plasterer x4
- Painter x2
- Floorer x2
- Tiler x2
- Water proofer x1
- Plumber x3
- Electrician x2
- Cabinet maker x2
- Concreter x3
- Renderer x2
- Identify and determine quantities required for plant and equipment
- Scaffolding
- Scissor lift / elevated platform
- Crane
- Concrete pump truck
- Skip bin
- Site toilet