The importance of risk analysis

The importance of risk analysis

As mentioned in Chapter 1, in terms of risk, too many feasibility studies and appraisals of megaprojects assume projects to exist in a predictable Newtonian world of cause and effect where things go according to plan. In reality, the world of megaproject planning and implementation is a highly stochastic one where things happen only with a certain probabil- ity and rarely turn out as originally intended. The failure to reflect the probabilistic nature of project planning, implementation and operation is a central cause of the poor track record for megaproject performance documented above.1

It is fairly common in feasibility studies and appraisals of major trans- port and other infrastructure projects to make a mechanical sensitivity analysis examining the effect on project viability of hypothetical changes

in, for instance, construction costs, interest rates and revenues.2 The typical range for such sensitivity analysis is from +10 per cent to +20 per cent. It is, on the other hand, unfortunately rare that risk analysis is

made by identifying alternative future states of costs, revenues and effects and a probability distribution estimated for the likelihood that these states would actually occur. This information is required in order to estimate the expected values of costs, revenues and effects, or, in other words, the most likely development, including the associated variances. Approaching risk analysis in this way is essential in order to curb what has been called ‘appraisal optimism’ and to give decision makers a more realistic view of the likely outcome of projects, instead of the incomplete and misleading view on which decisions are often based today.3 Risk analysis is also the basis for risk management, that is the identification of strategies to reduce risks, including how to allocate them to the parties involved and which risks to transfer to professional risk management institutions, namely in- surance companies. In this chapter we describe how risk was treated in the Channel, Great Belt, Øresund and other projects. In addition,

review the implications of risk for costs and financing. Finally, we spell out the lessons to be learnt regarding risk.4

Channel tunnel, Great Belt, Øresund and other projects

When Eurotunnel went public as a company in 1987, investors were told that the project was relatively straightforward. Regarding risk, the prospectus read:

Whilst the undertaking of a tunnelling project of this nature necessarily involves certain construction risks, the techniques to be used are well proven… The Directors, having consulted the Maˆitre d’Oeuvre, believe that 10%… would be a reasonable allowance for the possible impact of unforeseen circumstances on construction costs.5

Two hundred banks communicated the figures for cost and risk to in- vestors, including a large number of small investors. As has been observed elsewhere, anyone persuaded in this way to buy shares in Eurotunnel in the belief that the cost estimate was the mean of possible outcomes was, in effect, misled.6 The cost estimate of the prospectus turned out to be a best possible outcome based on the unlikely assumption that everything would go according to plan with no delays, no changes in performance specifications, no management problems, no problems with contractual arrangements or new technologies or geology, no major conflicts, no po- litical promises not kept, and so on. The assumptions were, in other words, those of an ideal world. The real risks for the Chunnel venture were several times higher than those communicated to potential investors, as evidenced by the fact that the real costs of the project were higher by a factor of two compared with forecasts.

Similarly, before ratifying the Great Belt project, the members of the Danish Parliament were informed by the Minister of Transport regarding risk that:

I do not consider the uncertainty of the overall construction cost estimate for a fixed link across Great Belt to be larger than for other large bridge or tunnel projects carried out in this country.7

However, the cost of even the largest bridge and tunnel projects carried out in Denmark before the Great Belt link was less than a tenth of the original Great Belt budget, and none of these projects included a bored tunnel.8 So for reasons of size and innovation alone, the risks associated with the Great Belt link were more important than for any other trans- port infrastructure project in modern Danish history. In addition, the geological and technological risks – and hence the risks associated with

construction costs – were higher. Nevertheless, no financial or economic risk analysis was made for the Great Belt project.9 As in the case of the Channel tunnel, the cost estimate for the Great Belt link turned out to be optimistic and was closer to an unlikely best possible outcome than to a most likely one. With a cost overrun of 110 per cent for the Great Belt rail tunnel, risks caught up with the rail link, which proved non-viable and was rescued only by cross-subsidisation from the road link (see Chapter 4). Total construction costs were 54 per cent higher than forecast costs. But, unlike the Chunnel, it is taxpayers’ money that has been placed at risk at Great Belt and not investors’ money.

For the Øresund link, partial risk analyses were carried out. In one such analysis, a group of government officials assessed that given histor- ical experience a 50 per cent cost overrun ‘cannot be seen as an unreal- istic maximum estimate’ for the link.10 In addition, the group found the project financially non-viable even without this overrun, as did three other appraisals carried out by officials in the months before the project was presented to the Danish Parliament. Yet, when the Minister of Transport presented the project for ratification in 1991, none of this information was mentioned. Neither the proposed law nor the accompanying comments contained any information about risks of non-viability.

When, more than two years later, it became publicly known that such information existed and had been withheld from Parliament, the result was a sharp critique of the Minister of Transport by the Auditor- General of Denmark.11 The Auditor-General found that the assumptions on which the estimates of project viability were based ‘represent the economic assumptions that have to be made for the project to be self- financing’, that is the assumptions that would make the project seem viable on paper, and not the assumptions that would have reflected the most likely development.12 For later budgets, worked out by the state- owned enterprises responsible for construction of the Danish access links and the fixed link proper, the Auditor-General similarly found that it was ‘less evident’ that the budgets were within claimed levels of uncer- tainty.13 Moreover, the Auditor-General found that the risks regarding the future development of interest rates and financing costs had been ignored and that it ‘would have been natural’ to mention this in the project budgets.14

On this basis, the Auditor-General resolved to monitor the Øresund project and to carry out audits in order to establish whether the assumed basis for the project would actually be realised, including whether the project would, in fact, be self-financing as required by the Danish political agreement behind the project and by the agreement between Denmark and Sweden to build the link.15

The treatment of risk in the Channel tunnel, Great Belt and Øresund projects has clearly been inadequate. Even so, the organisational and institutional set-up of the Great Belt and Øresund links, as loan- and user-financed state-owned enterprises, may be improvements over earlier transport infrastructure projects in Denmark in terms of risk identifica- tion and allocation, because costs, revenues and viability have become more visible than in earlier projects, as have environmental impacts. Still, there is substantial scope for improvement for future projects as shown above and as will become clear from what follows. For other major projects – transport and non-transport alike – the conclusions are similar: the risks involved are high and are typically treated in a deficient, sometimes even deceptive, manner in feasibility studies and project appraisals, if treated at all. In a World Bank study of ninety-two projects, only a handful was found to contain ‘thoughtful’ risk analy- sis showing ‘good practice’.16 Appraisals of World Bank projects are typi- cally more complete and more rigorous than appraisals of other projects. Nevertheless, it is important to note that there are good examples as well. We have already mentioned in Chapters 2–4 the construction of the Paris South-East and Paris Atlantique high-speed rail lines.17 Also, the technologically high-risk Apollo aerospace programme is considered a classic success story of megaproject planning and implementation. The cost overrun on this us$21 billion project was only 5 per cent. Few know, however, that the original budget estimate included us$8 billion of con- tingencies.18 By allowing for risk with foresight, the programme avoided ending up in the type of large cost overrun that destabilises many major projects during implementation. The Apollo approach, with its realistic view of risks, costs and contingencies, should be adopted in more major

projects.

A typology of risks

The main sources of financial risk in major transport infrastructure projects are:

  • construction cost overruns induced by, for instance, government, client, management, contractor or accident;
  • increased financing costs, caused by changes in interest and exchange rates and by delays; and
  • lower than expected revenues, produced by changes in traffic volumes and in payments per unit of traffic.

Although less significant, financial risks are also related to costs of oper- ations, maintenance and management. From an economic point of view the main risks are cost overruns, delays and lower realised demand than that assumed during appraisal.

From an analytical point of view, it is expedient to identify the fol- lowing types of risk of relevance to both a financial and an economic perspective:19

. Project-specific risks;

. Market risks;

. Sector-policy (including force majeure) risks;

. Capital-market risks.

The two first types of risk include those that are conventionally associated with a project, and that have been in focus so far. As for project-specific risks, the conventional assumption is that their effect can be eliminated – at least in part – by risk pooling or risk spreading; see further below. This does not normally apply to market risks that are explained by more funda- mental events that affect economic activities in a similar way, for example the overall economic development in a country. Sector-policy risks arise from the fact that the outcome of a project is dependent on specific sector policies; for transport projects, for instance, complementary investments in access links, taxation of transport or other regulation of road transport or of the environment. Some of these risks can be identified and can also be eliminated by providing a stable regulatory environment and by proper contracting. These types of risk are not necessarily eliminated by having projects operated by state-owned companies. Ultimately, such companies serve the general public, and if changes in regulatory policies imply that a project cannot be used as originally envisaged, private parties, that is taxpayers, will be affected in a negative way, as would be the case if the project were to be operated by a private entity.

Capital-market risks are created through borrowing, in particular in the international market, in order to finance projects. Such risks mainly con- sist of two elements, interest rate risks and currency risks. The capital market is today able to provide financing on conditions that allow borrow- ers to protect themselves against currency and interest rate adjustments in the short and medium term. But, of course, such insurance comes at a cost.

The cost of risk

The condition that a project is associated with risks gives rise to an economic cost. People are normally risk-adverse and are prepared to pay something – an insurance – in  order  to  reduce  or  totally  elimi- nate risks. The cost of risk is an economic concept and reflects the

maximum amount that an individual is willing to pay to eliminate a particular type of risk, so that the future of a particular type of event would become risk free for that individual.20 In practice, different lev- els of riskiness associated with different types of investment are reflected in different minimum rates of returns, which are required in order to persuade individuals to commit their money.21 The lowest return is nor- mally required on government bonds; here the return is about 3–4 per cent in real terms, as these bonds are considered to be virtually risk free. Private-sector debentures are normally associated with a somewhat higher return, say 5–6 per cent in real terms. The return  on  equity, namely ownership capital with risk, starts at about this level, but may be- come much higher depending on the perceived riskiness of the enterprise concerned.22

The risk costs associated with investments in infrastructure can be expected to be high. There are two basic reasons for this. The first is the fact that an investment in a major infrastructure project is basically a sunk cost, that is it cannot be retrieved. Once, for example, a bridge has been built it cannot really be used for anything else, so if the decision to build the bridge turns out later to have been a poor one, it cannot be repaired. The second reason is that the benefits of investments are often highly correlated with economic growth. If economic growth is high, then the project will fare well; conversely if growth is poor, the project will perform poorly. As noted, overall economic performance affects the market risk of a project, particularly when seen in an economic perspective. From an economic viewpoint it is difficult to offer insurance against market risks within a country, as it affects everybody, that is the risks cannot be spread and pooled when seen in a national perspective.

That infrastructure investments are viewed as risky is also brought out by the experience of private-sector involvement in infrastructure projects through a concession. The available data suggest that financing for con- cession companies will only be forthcoming provided: (i) the equity makes up about 20 per cent to 30 per cent of the total financing requirements; and (ii) that those who invest in equity can be expected to receive a return of between 15 and 25 per cent in real terms and after tax.23 Assuming that the remainder of the capital, the long-term debt, can be mobilised at a real cost of 6 per cent, the implication is that the project will have to achieve a financial rate of return of about 7.5 per cent to 12 per cent in real terms (disregarding taxation effects).

The difference between the return required for this type of investment, say 9 per cent, and the return on a virtually risk-free investment, say government bonds at 4–5 per cent, can be viewed as a measure of the cost of risk associated with the project. It should be emphasised that this

type of cost is incurred not only when an infrastructure project is de- veloped through a private concession company. It is also present when the project is developed by a state-owned enterprise and the financing is secured through a sovereign guarantee. In the world of risk there is no such thing as a free lunch. The risk and its costs exist under any cir- cumstances, even if promoters of projects backed by sovereign guarantees often impart the impression to politicians and the general public that this is not the case, as happened for the Øresund and Great Belt links. Here the promoters seemed to hold this belief themselves. One high-ranking Danish Ministry of Transport official expressed it to us in the follow- ing way in his comments on an earlier draft of the manuscript for this book:

In my view you should mention [in the book] that the costs the private sector would demand to have covered for taking on the full risk [of projects] would make the projects more costly. Thus the advantage of financing the Great Belt and Øresund projects by a sovereign guarantee is that this lowered financing costs.24

Not only do we hold that sovereign guarantees hide financing costs instead of lowering them. We also hold that there are reasons to believe that the risk costs associated with financing could increase if the project is underwritten by a sovereign guarantee. The reason is that the guarantee will transfer most of the risks to taxpayers, that is risk bearers who can be assumed to be less able, on average, to protect themselves against risks than those persons who act in the capital market, hence increasing overall risk costs.

In addition, there is good reason to mention a point made by the World Bank that the money saved by lower interest rates on loans backed by sovereign guarantees may be offset by inefficiencies arising from relaxed discipline as a result of such guarantees. Lenders backed by sovereign guarantees have no, or much less, incentive for supervising projects than do commercial banks without such guarantees, resulting in relaxed pressure on project performance. According to the Bank it may take several percentage points of interest advantage to offset even moderate inefficiencies in terms of cost overruns and delays stemming from the inefficient supervision of projects.25 For the Great Belt link the direct interest advantage of a sovereign guarantee on loans is approximately 1 to 2 percentage points, depending on the size and riskiness of the non- guaranteed projects that one compares it with.26 For the Øresund link the interest advantage is of a similar size. If one were to compare interest on guaranteed loans against return on equity, the advantage would be higher.

The total risk costs associated with infrastructure projects can normally be expected to be substantial. Take, for instance, the Øresund link, which cost some d 17 billion (excluding access routes), and is expected to yield a financial return of about 5 per cent. Assume, for example, that the actual requirement is an additional 5 per cent, that is in total 10 per cent in order to ensure that the costs of risk also will be compensated for. Then the cost of risk is equal to about one third of the total investment, that is about d 6 billion. Whilst this example is not an exact calculation of the cost of risk, it illustrates how important it is to take risk into account in project planning and appraisal.

Strategies of risk assessment

The most consequential problem regarding risk analysis in megaproject feasibility studies and decision making is not the absence or inadequacy of risk analysis in itself, but the neglect of relevant downside probabilities in the calculation of project viability.27 To a wide extent, risk is simply dis- regarded in feasibility studies and appraisals by assuming what the World Bank calls the EGAP-principle, ‘Everything Goes According to Plan’.28 We explained above how the unrealistic EGAP-principle was used for the Channel, Great Belt and Øresund links and what the problems involved were.

A cure recommended here, when undertaking a feasibility study, is to substitute what we call the ‘MLD-principle’ for the EGAP-principle, MLD standing for ‘Most Likely Development’. The cure should be seen as part of a wider strategy for public-sector involvement in developing megaprojects, which is taken further in Chapters 10 and 11. By follow- ing the MLD-principle, the roles of feasibility study and appraisal are redefined from the optimistic and unrealistic everything-goes-according- to-plan estimation of project viability to the realistic and experience-based assessment of the most likely development of projects. Carrying out MLD appraisals, the focus is on identifying the most likely risks and the most risky parts in a given project in order to reduce these risks and, if possible, drop those parts. What the World Bank calls ‘switching values’ would be calculated for key variables, including environmental variables, under- stood as the level of the variable at which the project turns from viable to non-viable. The likelihood of switching values actually occurring would be estimated. In addition to this, what the Auditor-General of Sweden calls ‘threshold levels’ would be established for costs, revenues, environ- mental impacts and viability, namely levels that, if crossed, redefine the project as a new project that must be appraised and approved anew. The result of such measures would be more robust projects.

A further technique that should be made use of in feasibility studies sponsored by public-sector organisations is the analysis of worst-case sce- narios, a method frequently employed in the private sector. The basic idea is simple: identify negative conditions from the point of view of the project and analyse the implications for the project’s viability and financing. This approach is helpful for determining the robustness of the project, but also for identifying supplementary actions required in order to mitigate risks and ensure success. Worst-case scenarios may also be useful for identi- fying projects that should be dropped altogether since the risks and their implications appear to be all too significant.

Risk management

In addition to identifying risks carefully and making them visible, a main instrument for reducing the costs of risk is to prepare a risk management plan as part of a feasibility study. The purpose of such a plan is to identify how various risks are to be managed and by whom. In the public sector, the establishment of a credible risk management plan should be a part of the documentation required before any decision is taken on whether to go ahead with a project or not (see Chapter 11).29 Figure 7.1 shows the main elements involved in risk management.

The main challenge to the preparation of a risk management plan is to actually fully identify the scope for risk management, and to communicate that it is much wider than what is normally appreciated. To a large extent this lack of appreciation of the role and scope of proper risk analysis and management is due to the history of contracting for infrastructure facili- ties. Because contracting in the infrastructure sector has to a large extent been on behalf of the public sector, the contracting format has become dominated by public-sector thinking. A key aspect of public-sector be- haviour is thus that it is typically rule-based and not performance-based. In contracting, this is reflected in the fact that contracts typically are based on technical specifications being given to the contractor; the contractor’s task is to build according to these specifications and not necessarily to achieve a certain level of performance (for so-called build contracts, see Chapter 9). However, this also means that the incentive and scope for developing new techniques in order to reduce costs, to reduce certain types of risk, and so on are limited. Consequently, present contracting techniques to a considerable extent eliminate the possibility of managing risks. A main challenge to risk management will therefore be to change the present contracting format, as is further discussed in Chapter 10.

There are several basic approaches to be considered as part of a risk management plan, some of which are partially overlapping. One approach

Figure 7.1 The risk management process

Source: Council of Standards Australia and Council of Standards New Zealand, Risk Management, AS/NZS 4360:1995 (Homebush: Standards Australia and Wellington: Standards New Zealand, 1995), p. 11.

involves eliminating risk altogether. This applies, for example, to certain sector-policy risks, for which it, given the circumstances, may be possible for the entity responsible for undertaking a specific type of infrastructure project to enter into an agreement with the central or local government to

ensure that certain policy actions are not taken, or at least not taken with- out compensation. A second approach involves buying risk management services. This may be the approach used in order to deal with capital- market risks and it might also be available for what some consider as force-majeure risks.

A third approach involves allocating risks to parties who have an in- centive to reduce the negative impacts of risk, either by reducing the likelihood of the event or to reduce the negative impact itself, if the event were to occur. Again this applies to such events that are normally consid- ered to be of a force-majeure nature, although they may not necessarily be a major event. An example may be the occurrence of unexpected geologi- cal phenomena creating delays in the construction of a bridge or a tunnel. By allocating geological risks to contractors from the outset the result is likely to be a more thorough analysis of such risks before contracts are finalised and a faster and more effective containment of negative impacts should unexpected geological phenomena occur during construction. If, conversely, the owner accepts geological risks, or if the placement of such risks is unclear, experience shows this to be a sure road to delays and cost overrun, especially for projects with substantial underground work. Another example may be the occurrence of protest actions during the ini- tial construction phase of an infrastructure facility, where the likelihood of the actions actually taking place can be significantly reduced through specific measures, for instance by replacing the conventional, closed for- mat for megaproject development with a more open and transparent one and by paying adequate compensation to parties negatively affected by projects, as done in Boston’s Big Dig project.

The nature of project-specific risks is such that their costs can be elim- inated by appropriate pooling or risk spreading. There are several institu- tional arrangements to handle this. As has been demonstrated by Arrow and Lind, one approach to achieving effective elimination through risk spreading is to allocate project-specific risks to the public in general.30 A way to achieve this would be to operate the project as part of the public sector, or by securing the financing for the project by way of govern- ment guarantees. But also the private sector has instruments available to achieve risk spreading. One of the reasons for establishing specific project companies for undertaking large infrastructure projects is thus to enable widespread participation by the capital market in the project, thereby allowing individual investors to pool their investments, and al- lowing the specific risks of the project considered to be spread between many investors, and thereby permitting the aggregate cost of this risk to be reduced.

The most difficult risks to manage are, as mentioned, market risks. One reason is that such risks are quite different when seen in an economic perspective from when seen from a financial point of view. As a rule, the economic cost of a market risk cannot be managed; the main issue to be considered is who should bear the cost of this risk, which is an important income distributional question and may also have institutional implications (see further Chapter 9).

Lessons regarding risk

As documented in this and the previous chapters, the risks associated with major infrastructure projects are substantial. Key factors contributing to risk are the facts that the investment will be irreversible and the viability highly dependent on general economic development. Given the magni- tude of the uncertainties involved, feasibility studies of major projects without risk analysis are less than useful since such studies will often de- ceive decision makers and the general public regarding the outcomes of projects. Risks cannot be eliminated from major projects, but they can be acknowledged and their impacts reduced through careful identification and by allocation of risks to those best suited to manage them.31

In most democracies the civil service has an obligation, defined by law, to provide the Cabinet and Parliament with ‘all relevant information’ pertaining to their decision taking and law making. Clearly, risks of cost overruns of 50–100 per cent on multibillion-dollar projects, together with large uncertainties regarding revenues and environmental impacts, are ‘relevant information’. Thus such information must be brought to the attention of politicians and the general public.

The following conclusions can be drawn regarding risk:

  • Public and private investors, parliaments, media and the general pub- lic are routinely inadequately informed and misled regarding the risks involved in megaprojects, cases in point being the Channel tunnel, Great Belt and Øresund projects;
  • A full risk analysis based on the MLD-principle (Most Likely Devel- opment) should be carried out as part of feasibility study and apprai- sal – undertaken by public-sector organisations – for any megaproject. In addition, a risk management plan should be prepared. Such risk

analysis and management would identify the most risky parts of a project. The objective is to reduce risks and to change or drop the most risky parts of the project. Finally, the aim is also to allocate risks appropriately to the involved parties;

  • Risk analysis should also comprise worst-case scenarios, in order to illustrate what happens if worst comes to worst. The experience with flooding and fire in the Great Belt rail tunnel illustrates the pertinence of this point as do the cost overruns and fire in the case of the Channel tunnel;
  • Feasibility studies and risk analyses for future projects should be carried out together with considerations regarding the possible in- stitutional, organisational and financial set-ups for the project. The set-ups will substantially influence risks and costs, just as risks and costs may influence the set-ups. Institutional change may be a pre- requisite for risk reduction, as discussed further in Chapters 10 and 11;
  • Public financing or financing with a sovereign guarantee and no risk capital, as known from Great Belt and Øresund, does not reduce risk or risk costs. It only transfers risk from lenders to taxpayers, and so is likely to increase the total risks and costs of a project.
Order Now

Get expert help for Dealing with risk Assignment and many more. 100% safe, Plag free, 24X7 support, Order Online Now!

No Fields Found.
Universal Assignment (October 2, 2023) The importance of risk analysis. Retrieved from https://universalassignment.com/dealing-with-risk-assignment/.
"The importance of risk analysis." Universal Assignment - October 2, 2023, https://universalassignment.com/dealing-with-risk-assignment/
Universal Assignment July 11, 2022 The importance of risk analysis., viewed October 2, 2023,<https://universalassignment.com/dealing-with-risk-assignment/>
Universal Assignment - The importance of risk analysis. [Internet]. [Accessed October 2, 2023]. Available from: https://universalassignment.com/dealing-with-risk-assignment/
"The importance of risk analysis." Universal Assignment - Accessed October 2, 2023. https://universalassignment.com/dealing-with-risk-assignment/
"The importance of risk analysis." Universal Assignment [Online]. Available: https://universalassignment.com/dealing-with-risk-assignment/. [Accessed: October 2, 2023]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Categories

Get 90%* Discount on Assignment Help

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

Foundations of Communication Assessment 2 Instructions

Discussion task (Total grade – 10%)   Process Work (Steps to complete the task) Answer on the Assessment 2 Submission Document – Do not upload this instruction document. Requirements (important elements to include) lastname_firstname_studentID_COMS_Assess 2_semester_year. Process for Assessment discussion tasks NOTE: If you do not participate in the class discussions then

Read More »

Assessment Two Dos and Don’ts (Internal)

Do: Read the assessment instructions carefully Read the marking rubric carefully Understand the question – break it down Conduct research – record the reference details Read the topic materials about communication theories, forms and factors and refer to them Contribute to the discussions in class or no marks for the

Read More »

Unpacking the Question: Assessment Two

Studying at university requires you to become familiar with strategies to un-pack or breakdown a variety of assessment questions/tasks throughout your studies.  Task Example of integrating the discussion, research and theories. In the group discussion my group members (name them) stated that an advertisement for a beauty product would most

Read More »

MGMT0001 Introduction to Commerce Assessment

MGMT0001 Introduction to Commerce Assessment 2 (worth 30%) Due date:                  2:00pm (AWST) Friday 15th September 2023 Submission:              Via Turnitin assessment submission link (see ‘Assessment 2’ folder in ‘Assessments’ section of Blackboard). Additional Instructions: Part A (42 marks) Nathan is a well-known chef with years of experience cooking various cuisines. After

Read More »

ACCT5011: Accounting Systems in the Digital Age

Practical Assignment Guide, Semester 2, 2023 Due Date for Submission: Monday 11th September 2023 at 5.00 PM Please note that the Folio Assignment for ACCT5011 Accounting Systems in the Digital Age is an individual assessment task worth 30% of your total marks in the unit. Please refer to the online

Read More »

EC229- Review session

Assume two cities, A and B, that can’t trade between them. Each city produces its own coconuts for its local market. If suddenly trade is possible then: D) As we saw in class, the new price will be somewhere between the original price 𝑃_𝐴,𝑃_𝐵. Hence it is impossible for consumers

Read More »

Computing Theory COSC

Computing Theory COSC 1107/1105 Assignment 1: Fundamentals Assessment Type Individual assignment. Submit online via Canvas → As- signments → Assignment 1. Marks awarded for meeting re- quirements as closely as possible. Clarifications/updates may be made via announcements/relevant discussion forums. Due Date Week 6, Sunday 27th August 2023, 11:59pm Marks 125

Read More »

BE279 Applied Statistics and Forecasting

Strategy, Operations, & Entrepreneurship Group Essex Business School Module Code BE279 Module Title Applied Statistics and Forecasting Assessment Type Individual Report (2,000 word) Academic Year 2022/23, Spring Term Submission Deadline Refer to FASER Task Specific Guidance Please note that: Module Learning Outcomes On successful completion of the module, students will

Read More »

Learning Design Tool: Little Learners Level 1 sounds

Learning Design Tool: Little Learners Level 1 sounds. Prepared by Sara Hart Date 30th August, 2023 (feel free to leave this date as it is the AT2 due date) Brief description of Learning Design   Chooseit Maker: Create, edit and play personalised learning activities that can be used in your

Read More »

HUMN1041 PEOPLE, PLACE AND SOCIAL DIFFERENCE ASSIGNMENT

HUMN1041 PEOPLE, PLACE AND SOCIAL DIFFERENCE ASSIGNMENT 1 TEMPLATE This assignment is made up of three (3) parts, plus a reference list and appendix. Marks are allocated for each section, as follows: – 1 mark Please ensure that you provide your answers in this template, and provide a Reference list

Read More »

Model 3 Launch in Australia

Client Information Company Name Tesla Contact Name   Email   Phone Number   Address Level 14, 15 Blue St. North Sydney, NSW 2060 Australia Ad link & image Project Information Project Title Model 3 Launch in Australia Project Description (100 words) Highlight the uniqueness of the car. Show the superior

Read More »

MKT10009 Marketing and the Consumer Experience

School of Business, Law and Entrepreneurship Assessment Task – Assignment 2  MKT10009 Marketing and the Consumer Experience Semester 2, 2023. Assessment Type Analytical Report Associated Unit Learning Outcomes (ULO’s) 2, 3, 4 Group or Individual task Individual Value (%) 25% Due Date Monday 20th September at 10:00 AET – Enterthis

Read More »

ASSIGNMENT – 1st Evaluation

ASSIGNMENT – 1st Evaluation Date of Submission- 4TH SEP 2023 25 MARKS COMPARATIVE PUBLIC LAW Q. You are the new Central Minister for Urban Development who is keen to make major Indian cities as smart cities. You visit different countries like USA, UK, European Countries, Japan and other developed countries

Read More »

Corporate & Financial Due Diligence Report

[Name of the company] Note: Students should keep in mind that application of legal provisions (including Securities Regulations) and analysis of the same is important. Merely putting the facts and figures won’t fetch even a decent mark. Note: Students should only mention the broad area of business. This part should

Read More »

ECON1000 S2 2023 – Marking Guidance and FAQs on GTP

Students will be marked on the extent to which they specifically answer the question and provide clear, logical, well-reasoned and sufficient explanations. Here is a summary breakdown of how marks are allocated in this GTP: Part 1 [15 marks] §  Providing relevant observations from the information provided in the articles

Read More »

ECON1000 S2 2023 – GTP Brief

ECON1000 S2 2023 – GTP Brief A.  Context and Overview The Game Theory Presentation (GTP) is worth 30% of the final mark. GTP is a ‘take-home’ exercise with a set of tasks to do. The GTP is based on Lecture Topics: L1 and L2. You will have twenty (21) days

Read More »

Order #35042 Human Rights Research Essay

Draft due 26th Aug 2,500 words (excluding references and bibliography) Instructions: Structure: Title – The Tigray War: A Critical Analysis of What the Future Holds for Human Rights in the Region What can be done to ensure human rights violations will cease and be prosecuted? Expand on different actors and

Read More »

PMC1000: Applied Pathology

Assessment Task Sheet: Poster Presentation Date: Thursday 31st August 2023 | Weighting: 30% Assessment Task 2 You are required to develop a handout style resource (pamphlet or brochure) on a selected pathological condition which is aimed at first year student paramedics. You will need to use high quality peer reviewed

Read More »

Detailed Information: Reflective Assignment

Indigenous Peoples, Law and Justice Detailed Information: Reflective Assignment Due Date:                   Tuesday 5th September 2023 at 4:00 pm (AWST). Marks:                       30% of the total marks for this unit. Assignment:              The assignment will comprise two questions. Students must answer all parts of both questions. Examinable topics: The cultural immersion exercise and/or

Read More »

Indigenous Peoples, Law and Justice

Indigenous Peoples, Law and Justice Reflective Assignment Questions Instructions: The assignment comprises two questions. Students must answer all parts of both questions. Question 1: The proposed Referendum Question is asking Australians whether the Voice should be established. What is meant by the Voice? In May 2019, Professor Anne Twomey, an

Read More »

Cultural immersion activity

Context of Carrolup To support fellow Australian and truth telling. Third space = a spiritual an mental place, meeting point of many cultures all over the world to communicate and feel safe to merge thought and aspects of everyone’s individual culture to create a sense of what they want the

Read More »

High-Fidelity Mockup Design for a Employer / Company  Review Platform

Demo Task: High-Fidelity Mockup Design for a Employer / Company  Review Platform Project Overview: You are tasked with designing high-fidelity mockups for a  Employer / Company  review platform that serves both employers and employees/users. The platform’s goal is to provide a space where employees can share their experiences and opinions

Read More »

IMPLEMENT AND MONITOR ENVIRONMENTALLY SUSTAINABLE WORK PRACTICES

ASSESSMENT COVER SHEET (Please ensure this cover sheet is completed and attached on top of each assessment) QUALIFICATION CODE AND TITLE:  Certificate IV in Commercial Cookery UNIT CODE: BSBSUS401               TITLE: IMPLEMENT AND MONITOR ENVIRONMENTALLY SUSTAINABLE WORK PRACTICES               Student Number   Student Name   Assessor Name   Assessment Name and

Read More »

Data Analysis and Findings

Qualitative data analysis technique called thematic analysis includes reading the data collection and looking for patterns in the meaning of the data to determine the theme. Making sense of the data is an active reflexive process in which the researcher’s personal experience is important. On Instagram, though, any company can

Read More »

PHE5STL: Systems Thinking and Leadership

Assessment 2: Complex problem briefing paper instructions and submission link PHE5STL: Systems Thinking and Leadership Assessment 2: Complex, or messy, problem briefing paper Assignment type Briefing paper/policy advising paper Weighting 20% Word count / length 1,500 words Note: The word count does not included references however does include in-text citations

Read More »

Assessment 1 Week-6: UML Modelling for a shopping mall

Assessment 1(    ) Information and Rubric Subject Code  ICT505 Subject Name  Software Development Assessment Number and Title  Assessment 1 Week-6: UML Modelling for a shopping mall Assessment Type Lab Activity Length / Duration  45 Minutes Weighting %  10% Total Marks  100 Submission Online Submission Due Date Week-6 (Sunday 23:59) Mode

Read More »

The Geopolitical, Economic and Legal Environment  

Faculty of Business and Law Assignment Brief Mode E and R Regulations Module Title: The Geopolitical, Economic and Legal Environment     Assignment Number 2 Module Code: 7010SSL   Assignment Title Macro Analysis Report Module Leader: Dr. Bentil Oduro   Assignment Credits 10           Release Date:

Read More »

Paragraph Template: TEEL Structure

 With this example from the discussion board, you can see Courtney answered the question with all four elements very clearly. This gives a coherent answer using different kinds of information and academic integrity. Bias is a natural behaviour of tendency to be in favour or against something in particular. From

Read More »

Choosing the Perfect Event Theme

Choosing the Perfect Event Theme Theme selection is crucial to creating a memorable and meaningful graduation celebration for the class. This selection should reflect their accomplishments and identities. Graduation marks the end of a long period of hard work, commitment, and personal growth.  Therefore, choosing a theme that effectively captures

Read More »

Can't Find Your Assignment?

Open chat
1
Free Assistance
Universal Assignment
Hello 👋
How can we help you?