Solution: Analytics Project Project Management Plan

CASE STUDY NUR350 ASSESSMENT TASK

Analytics Project

Project Management Plan

Date: 22-10-2023
Author: Name Here
Version: 2.0


Project Management Plan (PMP)

This project management plan will outline the strategies and plans used to manage ‘analytics project’ for the Style-Hub organization. It will include the tasks such as project governance, management, planning, budget and controlling. It uses the existing CRM and cloud infrastructure for the deployment of the new solution for informed decision-making. This project management plan will be used by the project team to streamline the work and ensure that the project outcomes can be delivered within the constraints. This document can be reviewed in coordination with project sponsor for changes.

Project Details

 Project NameProject PhasePOL Number
Analytics projectPlanning phase2.0
Project Manager
Name Here
ApproverNameApproval Date
   
   
   

List of Reviewers

ReviewerRoleEndorsement Date
   

Version History

VersionDateComments
V0.1   
V0.2   

Contents

1.      Executive Summary. 5

2.      Introduction. 5

2.1.       Project Background. 5

2.2.       Project Objectives. 5

3.      Project Definition. 5

3.1.       Project Scope. 6

3.2.       Assumptions. 6

3.3.       Constraints. 7

4.      Project Management Deliverables. 7

4.1.       Overview.. 7

4.2.       Roles and Responsibilities. 7

4.3.       Deliverable Descriptions. 8

5.      Project Plan. 9

5.1.       Project Schedule and Delivery. 9

5.2.       Stage Descriptions. 10

5.3.       Build Cycles. 11

5.4.       Definition of Ready and Done. 11

5.5.       Deployment 11

6.      Project Governance. 11

6.1.       Project Team.. 12

6.2.       Decision Management 12

7.      Project Budget 12

8.      Project Management Controls. 14

8.1.       Risk Management 14

8.2.       Quality Management 14

8.3.       Project Tools. 14

9.      References. 15

Glossary

If you have any abbreviations used in your document, list here.

AbbreviationTermDescription
CRMCustomer relationship managementCRM is a software package used to manage the relationship with customers such as updates about their order, log of their complaints etc.
  KPIKey performance indicatorsThese are some measures defined by the project manager to manage the project performance and outcomes. For example, one of the major could be cost utilization in a task.
   
  1. Executive Summary

Project management plan sets a direction and helps to define the resources and capabilities for a project to reduce uncertainties and enhance work organization. This report aims to discuss the project management plan for analytics project in Style Hub, an established retail fashion business in Australia. It will describe the project background and scope to set familiarity with the project. It will discuss the roles and responsibilities of major stakeholders and plan through which the project is expected to be completed. It will emphasize on project governance and control so that intended outcomes can be achieved within project constraints and capabilities.

The successful implementation of ecommerce solution helped the organisation to transform the operations from a brick-and-mortar model and it effectively tapped into international markets, especially grabbing the attentions of customers in New Zeeland. Currently, the organisation has extensive product catalogue and robust customer base but it is facing challenges to adapt changes in customer preferences and inventories across multiple channels. The organization is unable to make use of extensive data available from marketing, sales and other business functions. Through the analytics project, the organisation aims to enable the executives for data-driven decisions and enhanced adaptability and automation in operations.

The project aims to implement an analytics solution that can extract relevant data from the database system and present on screen in the form of visualizations through Power BI tool. For the implementation of analytics solution, the project has following major objectives:

  • To provide real-time insights for operations and sales for informed decision-making.
  • To automate the process for follow-up emails, shipment notifications and updates and enhance customer experience and streamlined communication.
  • To upgrade the customer relationship management system with integration of personalized marketing capabilities and customer segmentation.
  • To provide an interactive dashboard with valuable insights on operations and strategies.
  • To enable the organisation for forecasting on demand of products and services.

The analytics project will provide an interactive dashboard to the executives in the organisation including essential upgrades and changes to existing software and cloud solutions so that they can automate the routine operations, develop insights on processes and assist the customers in their digital journey through supporting in forecasting. It has scope to assist the resources in informed decisions and enhance overall effectiveness and accuracy in decisions for competitive advantages.

  • Items In-Scope
  • The solution will be built on Microsoft Azure and leverage the capabilities of Power BI for data visualization.
  • The solution will provide a dashboard showing real-time insights on sales and operations and upgrades the existing customer relationship management module.
  • It has scope to automate shipment notification, follow-up emails and updates in operations and sales.
  • The project will provide the documentation of the software for easier maintenance and upgrade over the years if required.
  • There will be a training manual for the users so that they can productively resume work on new system.
  • The changes/ configuration of Azure cloud is not included in the scope.
  • Database related changes such as data migration and cleansing are not the part of the project. They can be managed in-house or by the internal teams.
  • Automation of workflows in marketing and other functions is not covered as part of the project. However, it can be done in second iteration of maintenance if required.
  • Research for customer segmentation and personalized marketing capabilities is responsibility of internal team. The project team is only responsible for mapping of requirements with existing CRM.
AssumptionDescription and impact of the assumption
Schedule of six month is sufficient for planning to deployment stage.Generally, analytics project takes 6-12 months so that it is assumed that the project will be delivered within six months. It will impact the project team for improved planning and commitment to the goals and help the organisation to plan for future activities.
Project team has required skills and capabilitiesIndividual in team is assumed to have required skills and expertise. It will help to ensure that individual can complete the assigned task effectively with a smaller number of rollbacks (Heagney, 2016).
Availability of stakeholder is high.Stakeholders are available on demand to overview the project progress and outcomes so that the changes can be considered immediately to avoid severe impacts.
Budget is sufficientThe project is assumed to be completed in allocated budget. It helps to reserve the budget for risk handling and encourage working on in-scope requirements.
Project scope is not changingThe scope of the project is not changing once the project is initiated. It
ConstraintDescription and impact of the constraint
CostThe project cost may vary with occurrences of risks and changes in scope
RiskRisks such as absenteeism of the resources, lack of expertise for some concepts and poor coordination can impact the execution.
ResourcesResources are not sufficient so that the team may need to assess the cloud and existing database thoroughly.
ScheduleProject has constraint of time, especially when there are changes in execution (Kerzner, 2022).
QualityQuality is required paramount to address large customer base and staff accounts.
  • Project Management Deliverables
    • Overview

The project has mainly three deliverables:

  • Analytics solution on Azure platform
  • Project documentation/ specification
  • User manual

Although, there are several intermediate deliverables throughout the project. They are:

  • Project charter and initiation document during project initialization
  • Plans for budget, schedule, work break down, scope, communication and risk management during planning stage.
  • Status and tracking reports, KPI document, quality documents and forecast results during execution and control phase (Besteiro et al., 2015).
  • Project specification and user manual at the project closing stage.

Following are major roles and responsibilities in the project:

Project manager

  • Defines the project scope and specification
  • Prioritize the workflow and assign tasks to other resources in team
  • Identify and manage risks and monitor the project progress
  • Collaborate and coordinate with resources for change approval (Marchewka, 2016)

Technical staff

  • Responsible to design the strategy and blueprint for deployment of analytics solution
  • Deliver iterative work in coordination with quality tester

Analyst

  • Assist the project manager in documentation and research practices
  • Support in work scheduling, communication and management practices

Quality tester

  • Test the solution against defined criteria for evaluation
  • Provide feedback to the technical staff for changes or improvement (Marchewka, 2016)
  • Interact with staff member in organization and enable insights into features and functions.

Asides of the project team, there are following resources from the organisation who are controlling approvals, budget and other capabilities:

Founder and CEO

  • Define strategic vision for the project
  • Suggest features and functions for the solution
  • Manage changes and improvements in the project

Chief data officer

  • Approve financial allocations
  • Devise mitigation plans for the risks if any arise
  • Oversee the entire project for the intended outcomes and performance.

Head of merchandising

  • Identify customer needs
  • Ensure relevancy of the products in physical and online stores
  • Provide data regarding product availability and sales potentials
  • Deliverable Descriptions
DeliverableDescriptionResponsible
Analytics solutionIt is the end-system required to the organisation for informed decision-making.Project manager
Project documentationIt includes details how the project is designed and implemented. It is useful when project is being maintained in future.Analyst
User manualIt includes instructions and diagrams to demonstrate how to use the system for configuration and routine operations (Kerzner, 2018)Technical staff
  • Project Plan
    • Project Schedule and Delivery

As the project schedule indicate, the project can be delivered within six months. It is starting on 1 November 2023 and ending on 1 April 2024.

  • Stage Descriptions
StageDescriptionActivitiesDeliverables
InitiationThis stage aims to initiate the analytics project in communication with stakeholders and identification of the major requirements. It mainly focuses on clarification of requirements and seeks approval from sponsors to start the project.Initial researchRequirement identificationKick-off meetingFeasibility studyProject initiation documentApproval for PID     
PlanningThis stage focuses on planning such as documentation of system specification and documentation of plans for schedule, cost, risk and other aspects.System specificationReview specificationProject planning document 
Design and executionThis stage focuses on activities aiming toward the delivery of the required solution. It includes backup of the existing systems and applications and design a new solution that meet the requirements. Once the design for change is prepared, the team starts implementing the system (Kerzner, 2017).Designing backup planCustomisation to systemsIdentification of vendorsRequest for proposalFinalisation of vendorProcurement of softwareSystem setupChanges in infrastructureEngage usersUpdate CRMAssess network infrastructureDesign final systemDesign security mechanismsIntegrate with main systemReview and update 
Monitoring and controlIt is a continuous process from the initial stage of the project. It aims to ensure that the project work is within the cost, time, scope and quality.Test sub-systemsWhole system testIdentify and suggest changesImprovement tasks 
ClosureThis stage focuses on exchange of the benefits and formal closure of the contract established between Style-Hub and project manager.Documentationtraining and developmentSigningHand-over of assets 
  • Build Cycles
CeremonyPurpose                                                                                                                                                     Frequency
Sprint planningIt has main purpose to plan the work for the upcoming sprint.,At beginning of each sprint
Daily stand-up  To update on what is done by team member and what they are doing and what needs to be done.Daily in morning
Sprint reviewit demonstrates the work completed so that stakeholders can review and provide feedbacksAt the end of each sprint
Sprint retrospectiveIt aims to reflect on sprint to learn what went well and what decisions could be made to improve the results (Sachdeva, 2016).At the end of the sprint but after sprint review
Backlog refinementTo review the items in product backlog and ensure that they are defined with accuracy for sprint planning.As required throughout the sprint
  • Definition of Ready and Done

Definition of ready includes following elements:

  • Description of each task of the project.
  • Acceptance criteria such as cost-effectiveness, time, quality and resource utilization
  • Identification of dependencies on external resources so that the project can be started effectively.
  • Estimation and priority of the tasks
  • Approvals for the execution

Definition of done includes:

  • The code and changes are reviewed and approved by the technical staff.
  • All the modules such as CRM, Sales and Operations are tested for their functions
  • Tasks are tested for their acceptance criteria
  • Documentation of specification and project deliverables
  • Approvals of the owner for the project outcomes

The project can be deployed using the batch model so that the stakeholders can test the available features and overall complexity of the system can be minimized. The project will use the predictable schedule for each task to ensure minimal disruptions. This model is also preferred to get sufficient time for the manual testing and validations. It also allows thorough auditing and documentation. The deployment strategy starts with evaluation and changes in existing infrastructure. For instance, the solution will be deployed on Microsoft Azure so that it will be checked for configuration and other requirements. Version control will be used to ensure that code is accessible to team. There is also focus on automation through continuous integration so that new features and functions can be evolved over the core system (Shahin et al., 2017). There will be use of the monitoring tools and techniques such as project management software, team communication tools and workflow controlling tools so that the team can work effectively. Rollback strategies are also considered so that rollback can be done quickly without impact the current progress to a higher degree.

  • Project Governance

CEO or Founder is a at head of the project as a sponsor. The sponsor governs the project for progress and outcomes against the defined constraints. The project manager monthly reports to the sponsor for the progress and on-demand reporting is used for immediate changes and risk management. Chief data officer has responsibility to govern the financial allocations. The project manager reports and request financial results with chief data officer at least once a month. The developers and other technical staff work under the project manager and they provide their weekly reports for review and directions in the project. Senior technical staff can monitor and manage the progress and alignment of the team members to ensure that they are working in right directions (Derakhshan et al., 2019). For any change in the project, approval from the project manager is required. If the change includes significant finance, scope and other aspects, then project manager can further process the request through the sponsor.

  • Project Team
Team NameTeam leader
Name HereName Here
Project nameDuration
Analytics project6 months
BackgroundThe project aims to design an analytics solution that can help the organization in informed decision-making by using sales and operations data. The team has expertise to cover the project and individual will get dedicated role and responsibility to deliver the project in high quality. The major stakeholders of the project are staff and executives of the business.
Mission and objectivesThe project team is doing the project for Style-Hub, a leading fashion retailer in Australia and New Zeeland. If the project is completed successfully, the executives such as founder and chief data officers will be able to use the data visualizations to support their decision-making process. The project benefits the organisation in automation and decision-making. The organization is expanding and now the conventional database solutions are not sufficient to develop insights about the data and market trends.
Budget and resourcesThe project is funded by the founder and a budget of $500000 is finalized for it. The organisation is allocating three resources, including one staff member to gather requirement for the new system. It also provides sample database and access to Azure cloud service and existing CRM. The organisation will provide a training of two days to develop understanding with existing system and requirements. The management support can be received from chief data officer.
  • Decision Management

The sponsor can make decisions regarding product feature and functions and assist the project manager for finalization of the specification. After that, the sponsor has rights to initiate the in-scope changes and govern the progress. Project manager is at head for the team who manages the decisions for changes in task allocation, role delegation and handling of most of the internal disrupts and issues in team. The financial decisions are taken by the chief data officer. The overall project-related decisions are centric to the project manager but the project manager can work with other resources such as senior developers to estimate the cost and approach (Joslin and Müller, 2016).

  • Project Budget

Summary cost of project-

Total budgeted cost: $425,780

Total actual cost: $383,202

Actual variance= $42578

Details of the project-

Name of the company: Style-Hub

Project name or ID: Analytics project (P101)

Project lead: Name here

Start date: 1 November 2023.

Following are major risks along with their impact, likelihood and possible approach to mitigate them:

Use of new technology: The project takes around 6 months. If there are changes in technology in between can cause financial loss. It can cause rework and rollback. It is rare to occur but it can impact the project moderately. It can be mitigating by setting the project scope and boundaries at beginning.

Cost constraint: the project has risk of budget overrun because of the change management. As there is minimal gap in assigned budget and budgeted amount, the changes can cause cost overrun issue (Chapman, 2019).

Internal conflicts: The conflicts of the team members can cause delays and poor quality. It is rare to occur but it can impact the project severely. It can be mitigating by establishing a formal channel for communication and coordination.

The project manager will govern the quality of the project against some specific criteria such as:

  • Cost of the task and actual cost consumed in a task
  • Productivity of the resources for the task
  • Attainment of the features or functions for the task
  • Dependency on other resources (Kerzner, 2017)
ToolPurpose
Microsoft ProjectTo manage and monitor the project schedule, cost and resource allocation. It is helpful to identify the critical path and introduce dynamic changes in schedule to meet the constraints.
Microsoft TeamIt will be used for the formal communication among the team. It helps them to share data and report to the manager instantly.
Email serviceIt can be used for communication with manager and senior executives. It helps to standardize the communication and share critical documents such as code of conduct, project related policies and terms.

Besteiro, E.N.C., de Souza Pinto, J. and Novaski, O., 2015. Success factors in project management. Business management dynamics4(9).

Chapman, R.J., 2019. The rules of project risk management: Implementation guidelines for major projects. Routledge.

Derakhshan, R., Turner, R. and Mancini, M., 2019. Project governance and stakeholders: a literature review. International Journal of Project Management37(1), pp.98-116.

Heagney, J., 2016. Fundamentals of project management. Amacom.

Joslin, R. and Müller, R., 2016. The relationship between project governance and project success. International journal of project management34(4), pp.613-626.

Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.

Kerzner, H., 2022. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Marchewka, J.T., 2016. Information technology project management: Providing measurable organizational value. John Wiley & Sons.

Sachdeva, S., 2016. Scrum Methodology. Int. J. Eng. Comput. Sci5(16792), pp.16792-16800.

Shahin, M., Babar, M.A. and Zhu, L., 2017. Continuous integration, delivery and deployment: a systematic review on approaches, tools, challenges and practices. IEEE access5, pp.3909-3943.

Order Now
Universal Assignment (October 15, 2024) Solution: Analytics Project Project Management Plan. Retrieved from https://universalassignment.com/solution-analytics-project-project-management-plan/.
"Solution: Analytics Project Project Management Plan." Universal Assignment - October 15, 2024, https://universalassignment.com/solution-analytics-project-project-management-plan/
Universal Assignment January 26, 2024 Solution: Analytics Project Project Management Plan., viewed October 15, 2024,<https://universalassignment.com/solution-analytics-project-project-management-plan/>
Universal Assignment - Solution: Analytics Project Project Management Plan. [Internet]. [Accessed October 15, 2024]. Available from: https://universalassignment.com/solution-analytics-project-project-management-plan/
"Solution: Analytics Project Project Management Plan." Universal Assignment - Accessed October 15, 2024. https://universalassignment.com/solution-analytics-project-project-management-plan/
"Solution: Analytics Project Project Management Plan." Universal Assignment [Online]. Available: https://universalassignment.com/solution-analytics-project-project-management-plan/. [Accessed: October 15, 2024]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

ECON20001 Assignment #2

Assignment #2 Due Monday September 30th 2pm AEST The assignment is marked out of 25 points. The weight for each part is indicated following the question text. Style requirements: This assignment requires the submission of a spreadsheet. Please keep THREE decimal places in your answers and include your spreadsheet as

Read More »

RES800 Assessment 1 – Research Question and Literature Review

Subject Title Business Research Subject Code RES800 Assessment Title Assessment 1 – Research Question and Literature Review Learning Outcome/s     Utilise critical thinking to analyse managerial problems and formulate relevant research questions and a research design   Apply research theories and methodologies to assist in developing a business research

Read More »

Assessment Task 2 Health advocacy and communication plan

Assessment Task 2 Health advocacy and communication plan Rationale and multimedia plan presentation Submission requirements Due date and time:         Rationale: 8pm AEST Monday 23 September 2024 (Week 11) Multimedia plan presentation: 8pm AEST Monday 30 September 2024 (Study Period) % of final grade:         50% of overall grade Word limit: Time

Read More »

MLI500 Leadership and innovation Assessment 1

Subject Title Leadership and innovation Subject Code MLI500 Assessment Assessment 1: Leadership development plan Individual/Group Individual Length 1500 words Learning Outcomes LO1 Examine the role of leaders in fostering creativity and innovation LO5 Reflect on and take responsibility for their own learning and leadership development processes Submission   Weighting 30%

Read More »

FPC006 Taxation for Financial Planning

Assignment 2 Instructions Assignment marks: 95 | Referencing and presentation: 5 Total marks: 100 Total word limit: 3,000 words Weighting: 40% Download and use the Assignment 2 Answer Template provided in KapLearn to complete your assignment. Your assignment should be loaded into KapLearn by 11.30 pm AEST/AEDT on the wdue

Read More »

TCHR5001 Assessment Brief 1

TCHR5001 Assessment Brief 1 Assessment Details Item Assessment 1: Pitch your pedagogy Type Digital Presentation (Recorded) Due Monday, 16th September 2024, 11:59 pm AEST (start of Week 4) Group type Individual Length 10 minutes (equivalent to 1500 words) Weight 50% Gen AI use Permitted, restrictions apply Aligned ULOS ULO1, ULO2,

Read More »

HSH725 Assessment Task 2

turquoise By changing the Heading 3 above with the following teal, turquoise, orange or pink you can change the colour theme of your CloudFirst CloudDeakin template page. When this page is published the Heading 3 above will be removed, but it will still be here in edit mode if you wish to change the colour theme.

Read More »

Evidence in Health Assessment 2: Evidence Selection

Evidence in Health Assessment 2: Evidence Selection Student name:                                                                    Student ID: Section 1: PICO and search strategy Evidence Question: Insert evidence question from chosen scenario here including all key PICO terms.       PICO Search Terms                                                                                                                                                                                                          Complete the following table.   Subject headings Keywords Synonyms Population  

Read More »

Assessment 1 – Lesson Plan and annotation

ASSESSMENT TASK INFORMATION: XNB390 Assessment 1 – Lesson Plan and annotation This document provides you with information about the requirements for your assessment. Detailed instructions and resources are included for completing the task. The Criterion Reference Assessment (CRA) Marking Matrix that XNB390 markers will use to grade the assessment task

Read More »

XNB390 Task 1 – Professional Lesson Plan

XNB390 Template for Task 1 – Professional Lesson Plan CONTEXT FOR LESSON: SOCIAL JUSTICE CONSIDERATIONS: Equity Diversity Supportive Environment UNIT TITLE:    TERM WEEK DAY TIME 1   5           YEAR/CLASS STUDENT NUMBERS/CONTEXT LOCATION LESSON DURATION         28 Children (chl): 16 boys; 12

Read More »

A2 Critical Review Assignment

YouthSolutions Summary The summary should summarise the key points of the critical review. It should state the aims/purpose of the program and give an overview of the program or strategy you have chosen. This should be 200 words – included in the word count. Critical analysis and evaluation Your critical

Read More »

PUN364 – Workplace activity Assignment

Assessment 1 – DetailsOverviewFor those of you attending the on-campus workshop, you will prepare a report on the simulated simulated inspection below. For those of you who are not attending, you will be required to carry out your own food business inspection under the supervision of a suitably qualified Environmental

Read More »

FPC006 Taxation for Financial Planning

Assignment 1 Instructions Assignment marks: 95 | Referencing and presentation: 5 Total marks: 100 Total word limit: 3,600 words Weighting: 40% Download and use the Assignment 1 Answer Template provided in KapLearn to complete your assignment. Your assignment should be loaded into KapLearn by 11.30 pm AEST/AEDT on the due

Read More »

Mental health Nursing assignment

Due Aug 31 This is based on a Mental health Nursing assignment Used Microsoft word The family genogram is a useful tool for the assessment of individuals, couples, and families.  It can yield significant data and lead to important, new patient understandings and insights as multigenerational patterns take shape and

Read More »

Assessment 2: Research and Policy Review

Length: 2000 words +/- 10% (excluding references)For this assessment, you must choose eight sources (academic readings and policy documents) as the basis of your Research and Policy Review. You must choose your set of sources from the ‘REFERENCES MENU’ on the moodle site, noting the minimum number of sources required

Read More »

HSN702 – Lifespan Nutrition

Assessment Task: 2 Assignment title: Population Nutrition Report and Reflection Assignment task type: Written report, reflection, and short oral presentation Task details The primary focus of this assignment is on population nutrition. Nutritionists play an important role in promoting population health through optimal nutritional intake. You will be asked to

Read More »

Written Assessment 1: Case Study

Billy a 32-year-old male was admitted to the intensive care unit (ICU) with a suspected overdose of tricyclic antidepressants. He is obese (weight 160kg, height 172cm) and has a history of depression and chronic back pain for which he takes oxycodone. On admission to the emergency department, Paramedics were maintaining

Read More »

Assessment Task 8 – Plan and prepare to assess competence

Assessment Task 8 – Plan and prepare to assess competence Assessment Task 8 consists of the following sections: Section 1:      Short answer questions Section 2:      Analyse an assessment tool Section 3:      Determine reasonable adjustment and customisation of assessment process Section 4:      Develop an assessment plan Student Instructions To complete this

Read More »

Nutrition Reviews Assignment 2 – Part A and Part B

This assignment provides you with the opportunity to determine an important research question that is crucial to address based on your reading of one of the two systematic reviews below (Part A). You will then develop a research proposal outlining the study design and methodology needed to answer that question

Read More »

NUR332 – TASK 3 – WRITTEN ASSIGNMENT

NUR332 – TASK 3 – WRITTEN ASSIGNMENT for S2 2024. DESCRIPTION (For this Task 3, the word ‘Indigenous Australians’, refers to the Aboriginal and Torres Strait Islander Peoples of Australia) NUR332 Task 3 – Written Assignment – Due – WEEK 12 – via CANVAS on Wednesday, Midday (1200hrs) 16/10/2024. The

Read More »

NUR100 Task 3 – Case study

NUR100 Task 3 – Case study To identify a key child health issue and discuss this issue in the Australian context. You will demonstrate understanding of contemporary families in Australia. You will discuss the role of the family and reflect on how the family can influence the overall health outcomes

Read More »

NUR 100 Task 2 Health Promotion Poster

NUR 100 Task 2 Health Promotion Poster The weighting for this assessment is 40%. Task instructions You are not permitted to use generative AI tools in this task. Use of AI in this task constitutes student misconduct and is considered contract cheating. This assessment requires you to develop scholarship and

Read More »

BMS 291 Pathophysiology and Pharmacology CASE STUDY

BMS 291 Pathophysiology and Pharmacology CASE STUDY Assessment No: 1 Weighting: 40% Due date Part A: midnight Friday 2nd August 2024 Due date Part B: midnight Sunday 29th September 2024 General information In this assessment, you will develop your skills for analysing, integrating and presenting information for effective evidence-based communication.

Read More »

Assessment Task: Health service delivery

Assessment Task Health service delivery is inherently unpredictable. This unpredictability can arise from, for example, the assortment of patient presentations, environmental factors, changing technologies, shifts in health policy and changes in division leadership. It can also arise from changes in policy within an organisation and/or associated health services that impact

Read More »

LNDN08002 Business Cultures Resit Assessment

LNDN08002 Business Cultures Resit Assessment Briefing 2023–2024 (Resit for Term 1) Contents Before starting this resit, please: 1 Assessment Element 1: Individual Report 1 Case Report Marking Criteria. 3 Assessment Element 2: Continuing Personal Development (CPD) 4 Guidance for Assessment 2: Reflection and Reflective Practice. 5 Student Marking Criteria –

Read More »

Assessment Task 2 – NAPLAN Exercise

Assessment Task 2 (35%) – Evaluation and discussion of test items Assessment Task 2 (35%) – Evaluation and discussion of test items AITSL Standards: This assessmeAITSL Standards: This assessment provides the opportunity to develop evidence that demonstrates these Standards: 1.2        Understand how students learn 1.5        Differentiate teaching to meet with

Read More »

EBY014 Degree Tutor Group 2 Assignment

  Assignment Brief Module Degree Tutor Group 2 Module Code EBY014 Programme BA (Hons) Business and Management with   Foundation Year Academic Year 2024/2025 Issue Date 6th May 2024 Semester Component Magnitude Weighting Deadline Learning outcomes assessed 2 1 2000 words Capstone Assessment 100% 26th July, 2024 1/2/3/4 Module Curriculum

Read More »

Can't Find Your Assignment?

Open chat
1
Free Assistance
Universal Assignment
Hello 👋
How can we help you?