Module 1 – Project Task 1.3 – Prepare a Contract 2

Table of Contents

Module 1 – Project Task 1.3 – Prepare a Contract 2

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements 2

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority) 2

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria 3

Details of site accommodation 5

Small plant that would be required 5

The time allocation for the Supervisor to manage the project 5

A schedule of the estimated completion dates for the stages in the payment schedule 6

List of documents that is included in the contract to ensure it is a legal contract 6

Construction Contract Checklist 7

Introduction 7

B. General points 7

C. Design responsibility 8

D. Remedies for delay 9

E. Defective work 10

D. Contract price/payment provisions/tax 11

References 13

Module 1 – Project Task 1.3 – Prepare a Contract

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements

It was selected because we are building a new home and Master Builder Association Victoria has specified “New Home Building Contact” for this type of jobs.

Above contract is specifically design for new home construction.

The MBAV contract follows the reference and satisfied the requirements of the Domestic building contract Act and also adhere to the followings Australian Standards:

  • AS 4000 General conditions of contract
  • AS 2124 General conditions of contract

The builder must also provide Domestic Building Insurance as a contract exceeds more than

$16,000.

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority)

  • Master Builder Association of Victoria
  • Consumer Affairs
  • Legal Practitioner

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria

Section 31(1)(r) of the Domestic Building Contracts Act 1995

This checklist must be included in major domestic building contracts entered into from 1 September 2016 in substantially the same form or to the same effect as follows.

Before signing this legally binding contract, check this list:

If the cost of the building work is more than $16,000, has an insurance policy or certificate of currency for domestic building insurance covering your project been issued and provided to you? (Note: If not, the contract is conditional upon you receiving either an insurance policy or a certificate of currency for domestic building insurance.)Yes
No
If this contract is conditional upon you receiving written approval for finance, have you obtained such approval?Yes
No
Have you appointed a private building surveyor or has a municipal building surveyor been engaged? (Note: If not, you will need to choose and engage a building surveyor before your building work starts so that a building permit can be issued for your building work.)Yes
No
If you answer ‘NO’ to any of the following questions that apply to your building project, you are not ready to sign the contract:*
Have you had this contract long enough to read and understand it?Yes
No
Have you been provided with evidence that the builder named in this contract is registered with the Victorian Building Authority?Yes
No
Are the price and progress payments clearly stated?Yes
No
Do you understand how the price is calculated and may be varied?Yes
No
Has the builder assessed the suitability of the site for the proposed works? If tests are necessary, have they been carried out?Yes
No
If a deposit is payable, is it within the legal limit?
The maximum under the Domestic Building Contracts Act 1995 is: 10% if the price is less than $20,000, or 5% if the price is $20,000 or more.
Yes
No
Is the work shown and described clearly in the contract, plans and specifications and any other relevant documents (such as engineering computations or soil report)?Yes
No
Are your special requirements or standards of finish included in the plans and specifications?Yes
No
Are the commencement date and completion date clearly stated or capable of being worked out?Yes
No
Do you understand the procedure for extensions of time?Yes
No
Are any ‘provisional sums’ or ‘prime cost items’ clearly stated in the schedules and understood by you?Yes
No
Do you understand the procedure for variations of plans and specifications?Yes
No
Do you understand the circumstances in which you can end the contract?Yes
No
Did your builder give you a copy of the Domestic Building Consumer Guide?Yes
No
If yes, insert the date on which you were given a copy of this guide dd/mm/yyyy
Have you read the Domestic Building Consumer Guide and the related information at consumer.vic.gov.au/buildingguide?Yes
No

This checklist does not form part of the contract.

I/we have read and completed this checklist:

Signature/s
Date dd/mm/yyyy

* Note: Not all of these questions will apply to a domestic building contract that covers a limited scope of work, for example, a contract that is limited to the preparation of building plans and specifications. (Victoria, 2016)

Details of site accommodation

A domestic site like this will not be requiring site accommodation. However, if site is located in a remote location a nearby caravan park or hotel or motel can be use as a temporary site accommodation.

A small plant that would be required

Some of the small plants are required as follows:

  • Excavator
  • Dingo
  • Generator
  • Compressor
  • Small Crane
  • Cement Mixer
  • Battery powered tools.
  • Scissor lift
  • Duct Lifter
  • Scaffold
  • Shoring
  • Ladders
  • Gates

The time allocation for the Supervisor to manage the project

Time allocation for supervisor is 6 months to complete the build or 164 x days of schedule work.

A schedule of the estimated completion dates for the stages in the payment schedule

Timeframe in weeksPercentageAmountStage of build
2 Weeks0%$0Pre-contract
2 Weeks5%$16,000Deposit
4 Weeks10%$32,000Base Stage
4 Weeks15%$48,000Frame Stage
6 Weeks35%$112,000Lockup Stage
4 Weeks25%$80,000Fixing Stage
2 Weeks10%$32,000Final Stage

List of documents that is included in the contract to ensure it is a legal contract

List of documents as follows:

  • Soil Report
  • Energy Report
  • Engineering
  • Architectural Drawings
  • Planning Permit (if required)
  • Project Specifications

Construction Contract Checklist

Introduction

The purpose of this checklist is not to replace a review of the construction contract, but is intended to be used following such a review in order to check that all the key areas of the contract have been addressed. It is not essential to obtain positive answers to all the questions below in order to be able to give a contract a positive review, but hopefully the checklist will be useful in identifying areas of the contract which require further attention.

B. General points

  1. Has a full set of the contractual documents been provided for review?
  2. Does there appear to be any inconsistencies or any potential for inconsistencies between any of the contractual documents, e.g., two documents may cover the same area?
  3. Have all areas of the contract which need to be checked by a technical adviser been identified in the review, e.g.:
    1. technical aspects;
    2. employer obligations;
    3. rely on information;
    4. performance tests;
    5. all limits on liabilities; and
    6. Levels of liquidated damages?
  4. Has the contract been entered into? [If so, has it been executed as a deed?]
  5. Is the contract unconditional?
  6. Is there or has there previously been any interim arrangement in place between the employer and the contractor, e.g., work may have commenced under a letter of intent? If so, what are the implications of this ongoing or previous arrangement?
  7. What law governs the contract? Has advice been taken on the implications of this choice of law?

Is the contract based on one of the well-known standard forms of contract e.g. I Mech E or FIDIC?

C. Design responsibility

  1. What is the level of duty of care assumed by the contractor in respect of design? Is it an absolute obligation or only an obligation to use reasonable skill and care?
  2. Does the contract identify “performance criteria” which the plant when completed is required to meet? Is the contractor’s obligation to meet these criteria an overriding obligation or is it subject to a contractor’s duty only to use reasonable skill and care if such a duty of care is specified in the contract?
  3. What responsibility does the employer assume in respect of any designs, plans or technical information provided by him to the contractor?
  4. As regards any design/information provided by the employer, does the contract require the contractor to check this information and to assume responsibility for errors which could have been discovered by an experienced contractor?
  5. Is the contractor entitled to rely on the accuracy of any of this information (normally referred to as rely on information)? If so, does the employer have adequate recourse against the third parties who may have provided this information originally? (NB all rely on information will need to be checked by a technical adviser).
  6. Does the contract provide a mechanism for the employer to be able to review the detailed design of the contractor as and when it is produced?
  7. Are there adequate time periods provided for in the contract in order for the employer to carry out such review?
  8. If the detailed design is to be reviewed by the employer, by reference to what criteria is such approval to be made?
  9. Does the contract provide in respect of any design review and generally that approval by the employer does not release the contractor from any liability which he might otherwise have in respect of the design?
  10. If the review is to be carried out by a third party, such as an independent engineer, on behalf of the employer, is there provision elsewhere for a duty of care deed to be executed by that third party in favor of the lenders?
  11. Does the contract provide for performance tests to be performed to check (inter alia) that the plant is capable of achieving the performance criteria (see C.(2) above)? These tests will need to be reviewed by a technical adviser.
  12. When does the contract provide for these tests to be carried out? (This is normally upon mechanical completion.)
  13. Is the passing of the performance tests a condition precedent to handover?
  14. What does the contract provide for in the event that there is a failure in the performance tests?
  15. What is the effect of the plant passing the performance tests? (e.g., this should not exclude the contractor from any ongoing liability.)

D. Remedies for delay

  1. Does the contract provide for the payment of liquidated damages in the event of delay? If so, at what rate and up to what maximum limits? (The level of these damages should impose an adequate incentive on the contractor to complete on time 10-25 per cent. of the contract price as a maximum limit is a reasonable guideline.)
  2. What is “completion” for the purposes of establishing the payment of liquidated damages? Ideally the performance tests should have been successfully completed before completion can take place.
  3. Are there any unusual terms contained in the liquidated damages clause, e.g., liquidated damages calculated as being a percentage of the unfinished part of the work or only payable if the other parts of the project are already in place?
  4. If the contract is governed by English law, does the contract entitle the contractor to claim for extensions of time for employer’s default? (If not, the liquidated damages provision may not be enforceable). What other matters entitle the contractor to claim an extension of time?
  5. Consider the impact of the governing law on liquidated damages.
  6. Does the contract provide for a clear right of the employer to terminate for prolonged delay (i.e., when the maximum limit of liquidated damages has been reached)?
  7. If the employer is entitled to terminate the contract for prolonged delay, what damages are recoverable from the contractor following such termination? Is any element of consequential loss recoverable?
  8. Is there a clause in the contract requiring the contractor to catch up any delay which arises and providing that failure to do so amounts to a breach of the contract?
  9. Is the payment of the contract price front end loaded? The technical adviser should be asked to comment on this. If the contractor receives the bulk of his payment up front, the incentive on him to complete the works may be significantly reduced.

E. Defective work

  1. What is the duty of care imposed by the contract in respect of materials and workmanship?
  2. Does the contract provide for the employer or engineer to be able to inspect the works as they are performed and to require the contractor to put right any defective work?
  3. Is there a defects liability period and, if so, for what period? Does the contract draw any distinction between different aspects of the work (e.g., between engineering and civil works)?
  4. What is the effect of any final certificate issued at the end of the defects liability period? Does the contractor try to exclude his liability in any way for any defects arising after the end of this period (e.g., is there an exclusive remedies clause)?
  5. What does the local law provide as regards a contractor’s residual liability for latent defects?
  6. If the contractor fails to remedy any work for which he is responsible, does the contract entitle the employer to employ a substitute contractor to do this work and then for the employer to recover his costs from the original contractor?
  7. Are there any caps on the liability of the contractor to put right any defective work? Does this cap apply to any re performance requirements imposed on the contractor prior to handover?
  1. What does the contract provide for in respect of defects remedied during the defects liability period, i.e., does a new defects period start to run in respect of the replaced part and/or is the overall defects liability period extended by the period of time during which the works were put out of use due to that particular defect?
  2. How does the contract deal with the responsibility for costs in the situation where the employer requires the contractor to uncover work on the grounds that he has a reasonable suspicion that there may be a defect, having identified a similar defect elsewhere in the works? It is not necessarily logical simply to allocate the costs of uncovering work by reference to whether or not a defect is discovered.
  3. Does the contract require the contractor to notify the employer/engineer prior to any work being covered up?
  4. Is the employer entitled to take over the plant if it is not operating as required by the terms of the contract (e.g., it has failed the performance tests) and recover liquidated damages in respect of the short falls in performance (“buy down” liquidated damages)?
  5. Does the contract exclude liability for consequential and/or economic loss?
  6. Is the employer entitled to deduct sums from interim invoices in respect of defective work?

D. Contract price/payment provisions/tax

  1. Except for clearly identified additional payments, is the contract price a fixed lump sum? Have all entitlements to additional payments been identified in the review?
  2. Is the contract price expressed to include all contingencies and not to be subject to revision to take account of any fluctuations?
  3. How are payments triggered? What is the time for payment? What interest is payable by the employer if there is delay in making payment?
  4. Does the contract provide for payment by reference to milestones? (If so, they should be reviewed by the technical adviser.)
  5. If payment is by milestones, does the contract deal with what is to happen where progress is delayed due to the employer’s default? (The contractor should not be entitled to a milestone payment in these circumstances simply because the employer’s default has prevented this milestone being achieved, since otherwise there is a danger of overpayment.)
  6. Is payment by reference to a pre agreed payment schedule? If so, in what circumstances is the employer entitled to adjust this schedule?
  7. Is the employer entitled to deduct sums for defective work or for the cost of repairs carried out by a replacement contractor?
  8. Does the contract price include any provisional sums? Are these subject to maximum limits?
  9. What is the size of the “project negative” gap throughout the contract, i.e., the gap between expenditure by the employer and value received by the project either in terms of engineering or on the ground? (This should be reviewed by a technical adviser.)
  10. Does the contract envisage amendments to take account of the requirements of export credit agencies?
  11. Does the contract provide for the contractor to supply sufficient evidence of work done with interim invoices in order for the employer to be able to check that payments are due under the contract?
  12. Does the contract provide for any retentions from payments to be made to the contractor?
  13. Is the employer responsible for any taxes otherwise payable by the contractor? If the employer is responsible for payment of such taxes, does the contract expressly exclude penalties payable by the contractor and is there provision for the contractor to reimburse to the employer any tax credits subsequently recovered? (PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008)

References

PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008. Construction Contract Checklist. [Online]
Available at: http://www.worldbank.org/ppp
[Accessed 25 June 2021].

Victoria, C. A., 2016. Director of Consumer Affairs Victoria. [Online]
Available at: consumer.vic.gov.au/buildingindustry
[Accessed 25 June 2021].

Universal Assignment (June 2, 2025) Module 1 – Project Task 1.3 – Prepare a Contract 2. Retrieved from https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/.
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - June 2, 2025, https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
Universal Assignment June 8, 2022 Module 1 – Project Task 1.3 – Prepare a Contract 2., viewed June 2, 2025,<https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/>
Universal Assignment - Module 1 – Project Task 1.3 – Prepare a Contract 2. [Internet]. [Accessed June 2, 2025]. Available from: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - Accessed June 2, 2025. https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment [Online]. Available: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/. [Accessed: June 2, 2025]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

NUR1120 | Burden of Disease and Health Equity

Assessment Item Task SheetCourse code andnameNUR1120 | Burden of Disease and Health Equity Assessment itemand nameAssessment Three | ReportDue date and time Week 11 | 22/04/2025 at 2359 hours AESTLength 1400 words (+/- 10% in each section) – includes in-text references, but not reference list.Marks out of:Weighting:80 Marks50%Assessed CourseLearning Outcomes(CLO)CLO1,

Read More »

PSY1040 Portfolio: Cultural Responsiveness & Self-Awareness

Course Code and NamePSY1040: An Introduction to Cultural Safety in PracticeAssessment Item Number and NameAssessment 2: PortfolioAssessment Item TypePortfolio PSY1040 Portfolio: Cultural Responsiveness & Self-AwarenessDue Date & TimeTuesday, 29 April 2025 (Week 12), 11:59pmLength2000 words – an average of 400 words per task.Marks and WeightingMarked out of: 100Weighting: 50%Assessed Course

Read More »

Innovative Digital App Development Report

OVERALL DESCRIPTION OF TYPE OF ASSIGNMENT Assessment 1- Type of Assignment Individual Written Report Details Individual Written Report 3,000 words (500 words of the Report is Contextualisation) Weighting of Assessment : 70% INDIVIDUAL MARK Learning outcomes assessed by Assessment: 1, 2, 3 and 4 – See Module Listings of Learning

Read More »

Tourism Trends and Investment Decisions: A Comparative Study

Assignment TaskYou are a strategist working for a major hospitality group based in Australia. The company is planninginternational expansion, and the board has asked you to compile a report to identify the most suitablelocation for the project. The board has shortlisted two international locations (which will be allocatedto you by

Read More »

EC502 Language and Literacy in the Early Years

EC502 Language and Literacy in the Early Years Unit Code/Description EC502 Language and Literacy in the Early Years Course/Subject Bachelor of Early Childhood Education Semester March 2025 Assessment Overview   Unit Learning Outcomes Addressed 1, 2, 3 Assessment Objective Assessment 1: Poster Including an Invigilated stage in Week 3. Due

Read More »

EC501 Early Childhood Learning and Development

Unit Code/Description EC501 Early Childhood Learning and Development Course/Subject Graduate Diploma in Education (early childhood) Semester S 1, 2025 Assessment Overview   Unit Learning Outcomes Addressed 1, 2, 3 Assessment Objective In this assessment, student are required to select one of the case studies provided and critically analyze the child’s

Read More »

JSB172: Professional Academic Skills

JSB172: Professional Academic SkillsAssessment: Workplace Report and Presentation Weight: 50%Due date: Friday 30th May 11:59pm Length: 1,750 words (+/- 10 %) / 5minutesPurpose/Learning Objectives:This assessment relates to Learning Outcomes 1, 2, 3, and 4: Task:Your task is to write a Workplace Report identifying how to address the topic/issue chosen or

Read More »

2015PSY Developmental Psychology Assignment

2015PSY Developmental Psychology Assignment 2025 2015PSY Developmental Psychology Assignment Assignment MaterialsAssignment Information Sheet & Marking Criteria.pdf (this document)Assignment Template.docx (template)Example Assignment.pdf (HD exemplar)Due Date: Friday 16 May, 11:59PM (Week 10)Weighting: Marked out of 100 (worth 30% of course grade)Word Count: 1,500 words maximum(inclusive of main text, headings, in-text citations; excluding

Read More »

Principles of Economics Federal Budget

Principles of Economics Short-answer Assignment V1 (20% of final mark) The assignment consists of four questions.  You should allocate at least half a page (or 250 words) to each answer or 1000 words for all four answers depending on the nature of and/or marks allocated for the question/s. You may

Read More »

LML6003 – AUSTRALIA’S VISA SYSTEM 1 (FAMILY AND OTHERVISAS)

Graduate Diploma in Migration Law LML6003 – AUSTRALIA’S VISA SYSTEM 1 (FAMILY AND OTHER VISAS) Assessment Task 2 – Semester 1, 2025 LML6003 – AUSTRALIA’S VISA SYSTEM 1 (FAMILY AND OTHERVISAS) Instructions: 1. Students must answer all questions as indicated. Make certain all answers are clearly labelled. 2. Make certain

Read More »

Construction Cadetships in the Australian Construction Industry

REPORT TOPICPrepare an Academic Report on the following:‘Construction Cadetships in the Australian Construction Industry’.The report should encompass the following: Your personal evaluation and critique of the key findings in your report including your evaluation of construction cadetships, yourfindings in relation to potential issues/problems with cadetships and your recommendations to improve

Read More »

Assessing Corporate Governance and its Significance

Assessing Corporate Governance and its Significance: A Case Study Analysis Overview: Accounting irregularities have cost investors millions of dollars and, most importantly, adversely impacted their confidence in the financial system. While there have been remarkable improvements in regulatory supervision, auditing framework and reporting transparency, young graduates must assess major corporate

Read More »

Master of Professional Accounting and Accounting Advanced

Assessment 2 – Business Case (CVP) AnalysisUnit Code/Description ACC901 Accounting for Managerial DecisionsCourse/Subject Master of Professional Accounting and Master of Professional Accounting AdvancedSemester S1 2025 Assessment Overview Unit Learning OutcomesAddressed1,2,3,4 and 5Assessment Objective The primary objective of this assessment is to assess the students’ ability to apply CVPanalysis and relevant

Read More »

Urban Design Theory Essay writing

Essays are a major form of assessment at university. Through essays, you develop your understanding of discipline-specific content, strengthen your critical thinking, and develop your ability to translate that thinking into a persuasive written form. This assignment assesses your understanding of the following Unit Learning Outcomes: 1) understand the historic

Read More »

Statutory Interpretation of Disability Discrimination in NSW Law

Foundations of Law 70102 – Assessment Task 3 – Autumn 2025Statutory Interpretation and Research ExerciseDue: Thursday 22 May 2025 by 23.59Length: 2000 words (excluding the headings Part A, Part B and Part C, footnotes andbibliography. Any additional headings that you decide to use will be included in the wordcount)Weighting: 40%Task

Read More »

Engineering Career Readiness: Sustainability & Reflection

Objectives: The purpose of this assignment is to: Apply your learning in this unit to your development as an engineering graduate and your future career.Develop the ability to communicate yourself professionally.Develop an ability to reflect on your professional development, and identify any gaps in your capabilities.Unit Learning Outcomes: This task

Read More »

Child Study Report: Saif’s Development Across Key Domains

Child Study Report: Saif’s Development Across Key Domains Introduction This Child Study Report focuses on Saif, a 4-year and 6-month-old boy attending our childcare centre. Saif is an active, curious, and sociable child who engages enthusiastically in various activities. Over three weeks, multiple observations were conducted in different settings—such as

Read More »

2500 Words Insurance Case Study Analysis

Assessing Corporate Governance and its Significance: A Case Study Analysis Overview: Accounting irregularities have cost investors millions of dollars and, most importantly, adversely impacted their confidence in the financial system. While there have been remarkable improvements in regulatory supervision, auditing framework and reporting transparency, young graduates must assess major corporate

Read More »

Critical Reflections: Arts, Play & Mental Health

Peer Learning and DiscussionTask type Discussion Contribution Task description Contribute constructively to the formal weekly online discussions under the guidance of your moderator, in peer-to-peer learning. The purpose of the discussions is for students to explore and share ideas linked to the material being studied that week, and develop skills

Read More »

Indo-Pacific Health Challenge: Community Practice in Kiribati

Task type Indo-Pacific health challenge scenario Task description You will be presented with a real-world case scenario of a health challenge confronting an Indo-Pacific community that directly relates to the current climate emergency. You will analyse the scenario, exploring how community practice principles are being applied. You will then provide

Read More »

Assessment Task 1– SQL Report – Individual Assessment

MIS202 –Managing Data and Information – Trimester 1 2025Assessment Task 1– SQL Report – Individual AssessmentDUE DATE: Friday, 4 April, by 8:00pm (Melbourne time)PERCENTAGE OF FINAL GRADE: 30%WORD COUNT: Maximum 2000 wordsDescriptionPurposeThis task provides you with opportunities to learn the knowledge (GLO1 & ULO1) and skills (GLO 3 & ULO2;GLO4

Read More »

Assessment Category Infographic

Assessment # Title Assessment 1Assessment Category InfographicWeight 50%Length / Duration 500 words (excluding reference list)Individual / Group IndividualLearning OutcomesThis assessment evaluates your achievement of the following Unit Learning Outcomes:

Read More »

STM1001: Assignment 3 for Science/Health Stream Students

STM1001: Assignment 3 Science/Health Stream Students Only Academic Integrity Information In submitting your work, you are consenting that it may be copied and transmitted by the University for the detection of plagiarism. If you are unsure of your academic integrity responsibilities, please check the information provided in the Assessment Overview

Read More »

ACCG1000 Accounting for Decision Making Xero Assignment

1ACCG1000Accounting for Decision MakingXero AssignmentInformation packSession 2 2024Due Date: Friday 18th October 2024 at 11.55pm2Xero AssignmentIntroductionThe Xero assignment is designed to provide introductory accounting students with an overview of the Xero Accounting Software by completing a one-month accounting cycle for a fictional business. This is an online assignment worth 20%

Read More »

WRIT1001 Assessment Notification 2

6Final Essay: Rhetorical analysisDue: Friday 18 October 2024 at 23:59 (Sydney time)Length: 1500 words, worth 40% of the overall grade for the unitSubmit: as a Word document or PDF, via Canvas AssignmentMain question:● Present a scholarly essay that analyses the rhetoric used in arguments about thecontentious topic you have been

Read More »

WRIT1000 Assessment Four

Title: Self-ReflectionDue: Friday October 18 by 11:59PM.Length: 500 words (+/- 10%)Weight: 10% of the total gradeFormat: Times New Roman, double-spaced, 12pt. Your project should have the title“WRIT1000 Assessment Four – Self Reflection for xxxxxxx” where “xxxxxxxx” is yourstudent number. Please only submit Word documents (.doc or .docx). Turnitin doesnot recognise

Read More »

Written Assessment – Psychosocial Research Perspectives

Written Assessment – Psychosocial Research Perspectives TRIGGER WARNING: This is a case study of a real person. Katherine Knight was the first woman in Australia to receive a life sentence without parole after she decapitated and cooked her lover. If you think that you will have problems reading about this

Read More »

RES800 Assessment 1 – Research Question and Literature Review

Subject Title Business Research Subject Code RES800 Assessment Title Assessment 1 – Research Question and Literature Review Learning Outcome/s     Utilise critical thinking to analyse managerial problems and formulate relevant research questions and a research design   Apply research theories and methodologies to assist in developing a business research

Read More »

Can't Find Your Assignment?