Module 1 – Project Task 1.3 – Prepare a Contract 2

Table of Contents

Module 1 – Project Task 1.3 – Prepare a Contract 2

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements 2

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority) 2

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria 3

Details of site accommodation 5

Small plant that would be required 5

The time allocation for the Supervisor to manage the project 5

A schedule of the estimated completion dates for the stages in the payment schedule 6

List of documents that is included in the contract to ensure it is a legal contract 6

Construction Contract Checklist 7

Introduction 7

B. General points 7

C. Design responsibility 8

D. Remedies for delay 9

E. Defective work 10

D. Contract price/payment provisions/tax 11

References 13

Module 1 – Project Task 1.3 – Prepare a Contract

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements

It was selected because we are building a new home and Master Builder Association Victoria has specified “New Home Building Contact” for this type of jobs.

Above contract is specifically design for new home construction.

The MBAV contract follows the reference and satisfied the requirements of the Domestic building contract Act and also adhere to the followings Australian Standards:

  • AS 4000 General conditions of contract
  • AS 2124 General conditions of contract

The builder must also provide Domestic Building Insurance as a contract exceeds more than

$16,000.

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority)

  • Master Builder Association of Victoria
  • Consumer Affairs
  • Legal Practitioner

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria

Section 31(1)(r) of the Domestic Building Contracts Act 1995

This checklist must be included in major domestic building contracts entered into from 1 September 2016 in substantially the same form or to the same effect as follows.

Before signing this legally binding contract, check this list:

If the cost of the building work is more than $16,000, has an insurance policy or certificate of currency for domestic building insurance covering your project been issued and provided to you? (Note: If not, the contract is conditional upon you receiving either an insurance policy or a certificate of currency for domestic building insurance.)Yes
No
If this contract is conditional upon you receiving written approval for finance, have you obtained such approval?Yes
No
Have you appointed a private building surveyor or has a municipal building surveyor been engaged? (Note: If not, you will need to choose and engage a building surveyor before your building work starts so that a building permit can be issued for your building work.)Yes
No
If you answer ‘NO’ to any of the following questions that apply to your building project, you are not ready to sign the contract:*
Have you had this contract long enough to read and understand it?Yes
No
Have you been provided with evidence that the builder named in this contract is registered with the Victorian Building Authority?Yes
No
Are the price and progress payments clearly stated?Yes
No
Do you understand how the price is calculated and may be varied?Yes
No
Has the builder assessed the suitability of the site for the proposed works? If tests are necessary, have they been carried out?Yes
No
If a deposit is payable, is it within the legal limit?
The maximum under the Domestic Building Contracts Act 1995 is: 10% if the price is less than $20,000, or 5% if the price is $20,000 or more.
Yes
No
Is the work shown and described clearly in the contract, plans and specifications and any other relevant documents (such as engineering computations or soil report)?Yes
No
Are your special requirements or standards of finish included in the plans and specifications?Yes
No
Are the commencement date and completion date clearly stated or capable of being worked out?Yes
No
Do you understand the procedure for extensions of time?Yes
No
Are any ‘provisional sums’ or ‘prime cost items’ clearly stated in the schedules and understood by you?Yes
No
Do you understand the procedure for variations of plans and specifications?Yes
No
Do you understand the circumstances in which you can end the contract?Yes
No
Did your builder give you a copy of the Domestic Building Consumer Guide?Yes
No
If yes, insert the date on which you were given a copy of this guide dd/mm/yyyy
Have you read the Domestic Building Consumer Guide and the related information at consumer.vic.gov.au/buildingguide?Yes
No

This checklist does not form part of the contract.

I/we have read and completed this checklist:

Signature/s
Date dd/mm/yyyy

* Note: Not all of these questions will apply to a domestic building contract that covers a limited scope of work, for example, a contract that is limited to the preparation of building plans and specifications. (Victoria, 2016)

Details of site accommodation

A domestic site like this will not be requiring site accommodation. However, if site is located in a remote location a nearby caravan park or hotel or motel can be use as a temporary site accommodation.

A small plant that would be required

Some of the small plants are required as follows:

  • Excavator
  • Dingo
  • Generator
  • Compressor
  • Small Crane
  • Cement Mixer
  • Battery powered tools.
  • Scissor lift
  • Duct Lifter
  • Scaffold
  • Shoring
  • Ladders
  • Gates

The time allocation for the Supervisor to manage the project

Time allocation for supervisor is 6 months to complete the build or 164 x days of schedule work.

A schedule of the estimated completion dates for the stages in the payment schedule

Timeframe in weeksPercentageAmountStage of build
2 Weeks0%$0Pre-contract
2 Weeks5%$16,000Deposit
4 Weeks10%$32,000Base Stage
4 Weeks15%$48,000Frame Stage
6 Weeks35%$112,000Lockup Stage
4 Weeks25%$80,000Fixing Stage
2 Weeks10%$32,000Final Stage

List of documents that is included in the contract to ensure it is a legal contract

List of documents as follows:

  • Soil Report
  • Energy Report
  • Engineering
  • Architectural Drawings
  • Planning Permit (if required)
  • Project Specifications

Construction Contract Checklist

Introduction

The purpose of this checklist is not to replace a review of the construction contract, but is intended to be used following such a review in order to check that all the key areas of the contract have been addressed. It is not essential to obtain positive answers to all the questions below in order to be able to give a contract a positive review, but hopefully the checklist will be useful in identifying areas of the contract which require further attention.

B. General points

  1. Has a full set of the contractual documents been provided for review?
  2. Does there appear to be any inconsistencies or any potential for inconsistencies between any of the contractual documents, e.g., two documents may cover the same area?
  3. Have all areas of the contract which need to be checked by a technical adviser been identified in the review, e.g.:
    1. technical aspects;
    2. employer obligations;
    3. rely on information;
    4. performance tests;
    5. all limits on liabilities; and
    6. Levels of liquidated damages?
  4. Has the contract been entered into? [If so, has it been executed as a deed?]
  5. Is the contract unconditional?
  6. Is there or has there previously been any interim arrangement in place between the employer and the contractor, e.g., work may have commenced under a letter of intent? If so, what are the implications of this ongoing or previous arrangement?
  7. What law governs the contract? Has advice been taken on the implications of this choice of law?

Is the contract based on one of the well-known standard forms of contract e.g. I Mech E or FIDIC?

C. Design responsibility

  1. What is the level of duty of care assumed by the contractor in respect of design? Is it an absolute obligation or only an obligation to use reasonable skill and care?
  2. Does the contract identify “performance criteria” which the plant when completed is required to meet? Is the contractor’s obligation to meet these criteria an overriding obligation or is it subject to a contractor’s duty only to use reasonable skill and care if such a duty of care is specified in the contract?
  3. What responsibility does the employer assume in respect of any designs, plans or technical information provided by him to the contractor?
  4. As regards any design/information provided by the employer, does the contract require the contractor to check this information and to assume responsibility for errors which could have been discovered by an experienced contractor?
  5. Is the contractor entitled to rely on the accuracy of any of this information (normally referred to as rely on information)? If so, does the employer have adequate recourse against the third parties who may have provided this information originally? (NB all rely on information will need to be checked by a technical adviser).
  6. Does the contract provide a mechanism for the employer to be able to review the detailed design of the contractor as and when it is produced?
  7. Are there adequate time periods provided for in the contract in order for the employer to carry out such review?
  8. If the detailed design is to be reviewed by the employer, by reference to what criteria is such approval to be made?
  9. Does the contract provide in respect of any design review and generally that approval by the employer does not release the contractor from any liability which he might otherwise have in respect of the design?
  10. If the review is to be carried out by a third party, such as an independent engineer, on behalf of the employer, is there provision elsewhere for a duty of care deed to be executed by that third party in favor of the lenders?
  11. Does the contract provide for performance tests to be performed to check (inter alia) that the plant is capable of achieving the performance criteria (see C.(2) above)? These tests will need to be reviewed by a technical adviser.
  12. When does the contract provide for these tests to be carried out? (This is normally upon mechanical completion.)
  13. Is the passing of the performance tests a condition precedent to handover?
  14. What does the contract provide for in the event that there is a failure in the performance tests?
  15. What is the effect of the plant passing the performance tests? (e.g., this should not exclude the contractor from any ongoing liability.)

D. Remedies for delay

  1. Does the contract provide for the payment of liquidated damages in the event of delay? If so, at what rate and up to what maximum limits? (The level of these damages should impose an adequate incentive on the contractor to complete on time 10-25 per cent. of the contract price as a maximum limit is a reasonable guideline.)
  2. What is “completion” for the purposes of establishing the payment of liquidated damages? Ideally the performance tests should have been successfully completed before completion can take place.
  3. Are there any unusual terms contained in the liquidated damages clause, e.g., liquidated damages calculated as being a percentage of the unfinished part of the work or only payable if the other parts of the project are already in place?
  4. If the contract is governed by English law, does the contract entitle the contractor to claim for extensions of time for employer’s default? (If not, the liquidated damages provision may not be enforceable). What other matters entitle the contractor to claim an extension of time?
  5. Consider the impact of the governing law on liquidated damages.
  6. Does the contract provide for a clear right of the employer to terminate for prolonged delay (i.e., when the maximum limit of liquidated damages has been reached)?
  7. If the employer is entitled to terminate the contract for prolonged delay, what damages are recoverable from the contractor following such termination? Is any element of consequential loss recoverable?
  8. Is there a clause in the contract requiring the contractor to catch up any delay which arises and providing that failure to do so amounts to a breach of the contract?
  9. Is the payment of the contract price front end loaded? The technical adviser should be asked to comment on this. If the contractor receives the bulk of his payment up front, the incentive on him to complete the works may be significantly reduced.

E. Defective work

  1. What is the duty of care imposed by the contract in respect of materials and workmanship?
  2. Does the contract provide for the employer or engineer to be able to inspect the works as they are performed and to require the contractor to put right any defective work?
  3. Is there a defects liability period and, if so, for what period? Does the contract draw any distinction between different aspects of the work (e.g., between engineering and civil works)?
  4. What is the effect of any final certificate issued at the end of the defects liability period? Does the contractor try to exclude his liability in any way for any defects arising after the end of this period (e.g., is there an exclusive remedies clause)?
  5. What does the local law provide as regards a contractor’s residual liability for latent defects?
  6. If the contractor fails to remedy any work for which he is responsible, does the contract entitle the employer to employ a substitute contractor to do this work and then for the employer to recover his costs from the original contractor?
  7. Are there any caps on the liability of the contractor to put right any defective work? Does this cap apply to any re performance requirements imposed on the contractor prior to handover?
  1. What does the contract provide for in respect of defects remedied during the defects liability period, i.e., does a new defects period start to run in respect of the replaced part and/or is the overall defects liability period extended by the period of time during which the works were put out of use due to that particular defect?
  2. How does the contract deal with the responsibility for costs in the situation where the employer requires the contractor to uncover work on the grounds that he has a reasonable suspicion that there may be a defect, having identified a similar defect elsewhere in the works? It is not necessarily logical simply to allocate the costs of uncovering work by reference to whether or not a defect is discovered.
  3. Does the contract require the contractor to notify the employer/engineer prior to any work being covered up?
  4. Is the employer entitled to take over the plant if it is not operating as required by the terms of the contract (e.g., it has failed the performance tests) and recover liquidated damages in respect of the short falls in performance (“buy down” liquidated damages)?
  5. Does the contract exclude liability for consequential and/or economic loss?
  6. Is the employer entitled to deduct sums from interim invoices in respect of defective work?

D. Contract price/payment provisions/tax

  1. Except for clearly identified additional payments, is the contract price a fixed lump sum? Have all entitlements to additional payments been identified in the review?
  2. Is the contract price expressed to include all contingencies and not to be subject to revision to take account of any fluctuations?
  3. How are payments triggered? What is the time for payment? What interest is payable by the employer if there is delay in making payment?
  4. Does the contract provide for payment by reference to milestones? (If so, they should be reviewed by the technical adviser.)
  5. If payment is by milestones, does the contract deal with what is to happen where progress is delayed due to the employer’s default? (The contractor should not be entitled to a milestone payment in these circumstances simply because the employer’s default has prevented this milestone being achieved, since otherwise there is a danger of overpayment.)
  6. Is payment by reference to a pre agreed payment schedule? If so, in what circumstances is the employer entitled to adjust this schedule?
  7. Is the employer entitled to deduct sums for defective work or for the cost of repairs carried out by a replacement contractor?
  8. Does the contract price include any provisional sums? Are these subject to maximum limits?
  9. What is the size of the “project negative” gap throughout the contract, i.e., the gap between expenditure by the employer and value received by the project either in terms of engineering or on the ground? (This should be reviewed by a technical adviser.)
  10. Does the contract envisage amendments to take account of the requirements of export credit agencies?
  11. Does the contract provide for the contractor to supply sufficient evidence of work done with interim invoices in order for the employer to be able to check that payments are due under the contract?
  12. Does the contract provide for any retentions from payments to be made to the contractor?
  13. Is the employer responsible for any taxes otherwise payable by the contractor? If the employer is responsible for payment of such taxes, does the contract expressly exclude penalties payable by the contractor and is there provision for the contractor to reimburse to the employer any tax credits subsequently recovered? (PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008)

References

PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008. Construction Contract Checklist. [Online]
Available at: http://www.worldbank.org/ppp
[Accessed 25 June 2021].

Victoria, C. A., 2016. Director of Consumer Affairs Victoria. [Online]
Available at: consumer.vic.gov.au/buildingindustry
[Accessed 25 June 2021].

Universal Assignment (October 2, 2024) Module 1 – Project Task 1.3 – Prepare a Contract 2. Retrieved from https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/.
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - October 2, 2024, https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
Universal Assignment June 8, 2022 Module 1 – Project Task 1.3 – Prepare a Contract 2., viewed October 2, 2024,<https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/>
Universal Assignment - Module 1 – Project Task 1.3 – Prepare a Contract 2. [Internet]. [Accessed October 2, 2024]. Available from: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - Accessed October 2, 2024. https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment [Online]. Available: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/. [Accessed: October 2, 2024]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

ECON20001 Assignment #2

Assignment #2 Due Monday September 30th 2pm AEST The assignment is marked out of 25 points. The weight for each part is indicated following the question text. Style requirements: This assignment requires the submission of a spreadsheet. Please keep THREE decimal places in your answers and include your spreadsheet as

Read More »

RES800 Assessment 1 – Research Question and Literature Review

Subject Title Business Research Subject Code RES800 Assessment Title Assessment 1 – Research Question and Literature Review Learning Outcome/s     Utilise critical thinking to analyse managerial problems and formulate relevant research questions and a research design   Apply research theories and methodologies to assist in developing a business research

Read More »

Assessment Task 2 Health advocacy and communication plan

Assessment Task 2 Health advocacy and communication plan Rationale and multimedia plan presentation Submission requirements Due date and time:         Rationale: 8pm AEST Monday 23 September 2024 (Week 11) Multimedia plan presentation: 8pm AEST Monday 30 September 2024 (Study Period) % of final grade:         50% of overall grade Word limit: Time

Read More »

MLI500 Leadership and innovation Assessment 1

Subject Title Leadership and innovation Subject Code MLI500 Assessment Assessment 1: Leadership development plan Individual/Group Individual Length 1500 words Learning Outcomes LO1 Examine the role of leaders in fostering creativity and innovation LO5 Reflect on and take responsibility for their own learning and leadership development processes Submission   Weighting 30%

Read More »

FPC006 Taxation for Financial Planning

Assignment 2 Instructions Assignment marks: 95 | Referencing and presentation: 5 Total marks: 100 Total word limit: 3,000 words Weighting: 40% Download and use the Assignment 2 Answer Template provided in KapLearn to complete your assignment. Your assignment should be loaded into KapLearn by 11.30 pm AEST/AEDT on the wdue

Read More »

TCHR5001 Assessment Brief 1

TCHR5001 Assessment Brief 1 Assessment Details Item Assessment 1: Pitch your pedagogy Type Digital Presentation (Recorded) Due Monday, 16th September 2024, 11:59 pm AEST (start of Week 4) Group type Individual Length 10 minutes (equivalent to 1500 words) Weight 50% Gen AI use Permitted, restrictions apply Aligned ULOS ULO1, ULO2,

Read More »

HSH725 Assessment Task 2

turquoise By changing the Heading 3 above with the following teal, turquoise, orange or pink you can change the colour theme of your CloudFirst CloudDeakin template page. When this page is published the Heading 3 above will be removed, but it will still be here in edit mode if you wish to change the colour theme.

Read More »

Evidence in Health Assessment 2: Evidence Selection

Evidence in Health Assessment 2: Evidence Selection Student name:                                                                    Student ID: Section 1: PICO and search strategy Evidence Question: Insert evidence question from chosen scenario here including all key PICO terms.       PICO Search Terms                                                                                                                                                                                                          Complete the following table.   Subject headings Keywords Synonyms Population  

Read More »

Assessment 1 – Lesson Plan and annotation

ASSESSMENT TASK INFORMATION: XNB390 Assessment 1 – Lesson Plan and annotation This document provides you with information about the requirements for your assessment. Detailed instructions and resources are included for completing the task. The Criterion Reference Assessment (CRA) Marking Matrix that XNB390 markers will use to grade the assessment task

Read More »

XNB390 Task 1 – Professional Lesson Plan

XNB390 Template for Task 1 – Professional Lesson Plan CONTEXT FOR LESSON: SOCIAL JUSTICE CONSIDERATIONS: Equity Diversity Supportive Environment UNIT TITLE:    TERM WEEK DAY TIME 1   5           YEAR/CLASS STUDENT NUMBERS/CONTEXT LOCATION LESSON DURATION         28 Children (chl): 16 boys; 12

Read More »

A2 Critical Review Assignment

YouthSolutions Summary The summary should summarise the key points of the critical review. It should state the aims/purpose of the program and give an overview of the program or strategy you have chosen. This should be 200 words – included in the word count. Critical analysis and evaluation Your critical

Read More »

PUN364 – Workplace activity Assignment

Assessment 1 – DetailsOverviewFor those of you attending the on-campus workshop, you will prepare a report on the simulated simulated inspection below. For those of you who are not attending, you will be required to carry out your own food business inspection under the supervision of a suitably qualified Environmental

Read More »

FPC006 Taxation for Financial Planning

Assignment 1 Instructions Assignment marks: 95 | Referencing and presentation: 5 Total marks: 100 Total word limit: 3,600 words Weighting: 40% Download and use the Assignment 1 Answer Template provided in KapLearn to complete your assignment. Your assignment should be loaded into KapLearn by 11.30 pm AEST/AEDT on the due

Read More »

Mental health Nursing assignment

Due Aug 31 This is based on a Mental health Nursing assignment Used Microsoft word The family genogram is a useful tool for the assessment of individuals, couples, and families.  It can yield significant data and lead to important, new patient understandings and insights as multigenerational patterns take shape and

Read More »

Assessment 2: Research and Policy Review

Length: 2000 words +/- 10% (excluding references)For this assessment, you must choose eight sources (academic readings and policy documents) as the basis of your Research and Policy Review. You must choose your set of sources from the ‘REFERENCES MENU’ on the moodle site, noting the minimum number of sources required

Read More »

HSN702 – Lifespan Nutrition

Assessment Task: 2 Assignment title: Population Nutrition Report and Reflection Assignment task type: Written report, reflection, and short oral presentation Task details The primary focus of this assignment is on population nutrition. Nutritionists play an important role in promoting population health through optimal nutritional intake. You will be asked to

Read More »

Written Assessment 1: Case Study

Billy a 32-year-old male was admitted to the intensive care unit (ICU) with a suspected overdose of tricyclic antidepressants. He is obese (weight 160kg, height 172cm) and has a history of depression and chronic back pain for which he takes oxycodone. On admission to the emergency department, Paramedics were maintaining

Read More »

Assessment Task 8 – Plan and prepare to assess competence

Assessment Task 8 – Plan and prepare to assess competence Assessment Task 8 consists of the following sections: Section 1:      Short answer questions Section 2:      Analyse an assessment tool Section 3:      Determine reasonable adjustment and customisation of assessment process Section 4:      Develop an assessment plan Student Instructions To complete this

Read More »

Nutrition Reviews Assignment 2 – Part A and Part B

This assignment provides you with the opportunity to determine an important research question that is crucial to address based on your reading of one of the two systematic reviews below (Part A). You will then develop a research proposal outlining the study design and methodology needed to answer that question

Read More »

NUR332 – TASK 3 – WRITTEN ASSIGNMENT

NUR332 – TASK 3 – WRITTEN ASSIGNMENT for S2 2024. DESCRIPTION (For this Task 3, the word ‘Indigenous Australians’, refers to the Aboriginal and Torres Strait Islander Peoples of Australia) NUR332 Task 3 – Written Assignment – Due – WEEK 12 – via CANVAS on Wednesday, Midday (1200hrs) 16/10/2024. The

Read More »

NUR100 Task 3 – Case study

NUR100 Task 3 – Case study To identify a key child health issue and discuss this issue in the Australian context. You will demonstrate understanding of contemporary families in Australia. You will discuss the role of the family and reflect on how the family can influence the overall health outcomes

Read More »

NUR 100 Task 2 Health Promotion Poster

NUR 100 Task 2 Health Promotion Poster The weighting for this assessment is 40%. Task instructions You are not permitted to use generative AI tools in this task. Use of AI in this task constitutes student misconduct and is considered contract cheating. This assessment requires you to develop scholarship and

Read More »

BMS 291 Pathophysiology and Pharmacology CASE STUDY

BMS 291 Pathophysiology and Pharmacology CASE STUDY Assessment No: 1 Weighting: 40% Due date Part A: midnight Friday 2nd August 2024 Due date Part B: midnight Sunday 29th September 2024 General information In this assessment, you will develop your skills for analysing, integrating and presenting information for effective evidence-based communication.

Read More »

Assessment Task: Health service delivery

Assessment Task Health service delivery is inherently unpredictable. This unpredictability can arise from, for example, the assortment of patient presentations, environmental factors, changing technologies, shifts in health policy and changes in division leadership. It can also arise from changes in policy within an organisation and/or associated health services that impact

Read More »

LNDN08002 Business Cultures Resit Assessment

LNDN08002 Business Cultures Resit Assessment Briefing 2023–2024 (Resit for Term 1) Contents Before starting this resit, please: 1 Assessment Element 1: Individual Report 1 Case Report Marking Criteria. 3 Assessment Element 2: Continuing Personal Development (CPD) 4 Guidance for Assessment 2: Reflection and Reflective Practice. 5 Student Marking Criteria –

Read More »

Assessment Task 2 – NAPLAN Exercise

Assessment Task 2 (35%) – Evaluation and discussion of test items Assessment Task 2 (35%) – Evaluation and discussion of test items AITSL Standards: This assessmeAITSL Standards: This assessment provides the opportunity to develop evidence that demonstrates these Standards: 1.2        Understand how students learn 1.5        Differentiate teaching to meet with

Read More »

EBY014 Degree Tutor Group 2 Assignment

  Assignment Brief Module Degree Tutor Group 2 Module Code EBY014 Programme BA (Hons) Business and Management with   Foundation Year Academic Year 2024/2025 Issue Date 6th May 2024 Semester Component Magnitude Weighting Deadline Learning outcomes assessed 2 1 2000 words Capstone Assessment 100% 26th July, 2024 1/2/3/4 Module Curriculum

Read More »

Can't Find Your Assignment?

Open chat
1
Free Assistance
Universal Assignment
Hello 👋
How can we help you?