Module 1 – Project Task 1.3 – Prepare a Contract 2

Table of Contents

Module 1 – Project Task 1.3 – Prepare a Contract 2

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements 2

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority) 2

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria 3

Details of site accommodation 5

Small plant that would be required 5

The time allocation for the Supervisor to manage the project 5

A schedule of the estimated completion dates for the stages in the payment schedule 6

List of documents that is included in the contract to ensure it is a legal contract 6

Construction Contract Checklist 7

Introduction 7

B. General points 7

C. Design responsibility 8

D. Remedies for delay 9

E. Defective work 10

D. Contract price/payment provisions/tax 11

References 13

Module 1 – Project Task 1.3 – Prepare a Contract

Outline why the chosen contract type was selected, referring to relevant legislative and regulatory requirements

It was selected because we are building a new home and Master Builder Association Victoria has specified “New Home Building Contact” for this type of jobs.

Above contract is specifically design for new home construction.

The MBAV contract follows the reference and satisfied the requirements of the Domestic building contract Act and also adhere to the followings Australian Standards:

  • AS 4000 General conditions of contract
  • AS 2124 General conditions of contract

The builder must also provide Domestic Building Insurance as a contract exceeds more than

$16,000.

Details of who you consulted regarding the contract selection and/or preparation (industry association or consumer regulatory authority)

  • Master Builder Association of Victoria
  • Consumer Affairs
  • Legal Practitioner

Approved Domestic Building Contracts Checklist from Director of Consumer Affairs Victoria

Section 31(1)(r) of the Domestic Building Contracts Act 1995

This checklist must be included in major domestic building contracts entered into from 1 September 2016 in substantially the same form or to the same effect as follows.

Before signing this legally binding contract, check this list:

If the cost of the building work is more than $16,000, has an insurance policy or certificate of currency for domestic building insurance covering your project been issued and provided to you? (Note: If not, the contract is conditional upon you receiving either an insurance policy or a certificate of currency for domestic building insurance.)Yes
No
If this contract is conditional upon you receiving written approval for finance, have you obtained such approval?Yes
No
Have you appointed a private building surveyor or has a municipal building surveyor been engaged? (Note: If not, you will need to choose and engage a building surveyor before your building work starts so that a building permit can be issued for your building work.)Yes
No
If you answer ‘NO’ to any of the following questions that apply to your building project, you are not ready to sign the contract:*
Have you had this contract long enough to read and understand it?Yes
No
Have you been provided with evidence that the builder named in this contract is registered with the Victorian Building Authority?Yes
No
Are the price and progress payments clearly stated?Yes
No
Do you understand how the price is calculated and may be varied?Yes
No
Has the builder assessed the suitability of the site for the proposed works? If tests are necessary, have they been carried out?Yes
No
If a deposit is payable, is it within the legal limit?
The maximum under the Domestic Building Contracts Act 1995 is: 10% if the price is less than $20,000, or 5% if the price is $20,000 or more.
Yes
No
Is the work shown and described clearly in the contract, plans and specifications and any other relevant documents (such as engineering computations or soil report)?Yes
No
Are your special requirements or standards of finish included in the plans and specifications?Yes
No
Are the commencement date and completion date clearly stated or capable of being worked out?Yes
No
Do you understand the procedure for extensions of time?Yes
No
Are any ‘provisional sums’ or ‘prime cost items’ clearly stated in the schedules and understood by you?Yes
No
Do you understand the procedure for variations of plans and specifications?Yes
No
Do you understand the circumstances in which you can end the contract?Yes
No
Did your builder give you a copy of the Domestic Building Consumer Guide?Yes
No
If yes, insert the date on which you were given a copy of this guide dd/mm/yyyy
Have you read the Domestic Building Consumer Guide and the related information at consumer.vic.gov.au/buildingguide?Yes
No

This checklist does not form part of the contract.

I/we have read and completed this checklist:

Signature/s
Date dd/mm/yyyy

* Note: Not all of these questions will apply to a domestic building contract that covers a limited scope of work, for example, a contract that is limited to the preparation of building plans and specifications. (Victoria, 2016)

Details of site accommodation

A domestic site like this will not be requiring site accommodation. However, if site is located in a remote location a nearby caravan park or hotel or motel can be use as a temporary site accommodation.

A small plant that would be required

Some of the small plants are required as follows:

  • Excavator
  • Dingo
  • Generator
  • Compressor
  • Small Crane
  • Cement Mixer
  • Battery powered tools.
  • Scissor lift
  • Duct Lifter
  • Scaffold
  • Shoring
  • Ladders
  • Gates

The time allocation for the Supervisor to manage the project

Time allocation for supervisor is 6 months to complete the build or 164 x days of schedule work.

A schedule of the estimated completion dates for the stages in the payment schedule

Timeframe in weeksPercentageAmountStage of build
2 Weeks0%$0Pre-contract
2 Weeks5%$16,000Deposit
4 Weeks10%$32,000Base Stage
4 Weeks15%$48,000Frame Stage
6 Weeks35%$112,000Lockup Stage
4 Weeks25%$80,000Fixing Stage
2 Weeks10%$32,000Final Stage

List of documents that is included in the contract to ensure it is a legal contract

List of documents as follows:

  • Soil Report
  • Energy Report
  • Engineering
  • Architectural Drawings
  • Planning Permit (if required)
  • Project Specifications

Construction Contract Checklist

Introduction

The purpose of this checklist is not to replace a review of the construction contract, but is intended to be used following such a review in order to check that all the key areas of the contract have been addressed. It is not essential to obtain positive answers to all the questions below in order to be able to give a contract a positive review, but hopefully the checklist will be useful in identifying areas of the contract which require further attention.

B. General points

  1. Has a full set of the contractual documents been provided for review?
  2. Does there appear to be any inconsistencies or any potential for inconsistencies between any of the contractual documents, e.g., two documents may cover the same area?
  3. Have all areas of the contract which need to be checked by a technical adviser been identified in the review, e.g.:
    1. technical aspects;
    2. employer obligations;
    3. rely on information;
    4. performance tests;
    5. all limits on liabilities; and
    6. Levels of liquidated damages?
  4. Has the contract been entered into? [If so, has it been executed as a deed?]
  5. Is the contract unconditional?
  6. Is there or has there previously been any interim arrangement in place between the employer and the contractor, e.g., work may have commenced under a letter of intent? If so, what are the implications of this ongoing or previous arrangement?
  7. What law governs the contract? Has advice been taken on the implications of this choice of law?

Is the contract based on one of the well-known standard forms of contract e.g. I Mech E or FIDIC?

C. Design responsibility

  1. What is the level of duty of care assumed by the contractor in respect of design? Is it an absolute obligation or only an obligation to use reasonable skill and care?
  2. Does the contract identify “performance criteria” which the plant when completed is required to meet? Is the contractor’s obligation to meet these criteria an overriding obligation or is it subject to a contractor’s duty only to use reasonable skill and care if such a duty of care is specified in the contract?
  3. What responsibility does the employer assume in respect of any designs, plans or technical information provided by him to the contractor?
  4. As regards any design/information provided by the employer, does the contract require the contractor to check this information and to assume responsibility for errors which could have been discovered by an experienced contractor?
  5. Is the contractor entitled to rely on the accuracy of any of this information (normally referred to as rely on information)? If so, does the employer have adequate recourse against the third parties who may have provided this information originally? (NB all rely on information will need to be checked by a technical adviser).
  6. Does the contract provide a mechanism for the employer to be able to review the detailed design of the contractor as and when it is produced?
  7. Are there adequate time periods provided for in the contract in order for the employer to carry out such review?
  8. If the detailed design is to be reviewed by the employer, by reference to what criteria is such approval to be made?
  9. Does the contract provide in respect of any design review and generally that approval by the employer does not release the contractor from any liability which he might otherwise have in respect of the design?
  10. If the review is to be carried out by a third party, such as an independent engineer, on behalf of the employer, is there provision elsewhere for a duty of care deed to be executed by that third party in favor of the lenders?
  11. Does the contract provide for performance tests to be performed to check (inter alia) that the plant is capable of achieving the performance criteria (see C.(2) above)? These tests will need to be reviewed by a technical adviser.
  12. When does the contract provide for these tests to be carried out? (This is normally upon mechanical completion.)
  13. Is the passing of the performance tests a condition precedent to handover?
  14. What does the contract provide for in the event that there is a failure in the performance tests?
  15. What is the effect of the plant passing the performance tests? (e.g., this should not exclude the contractor from any ongoing liability.)

D. Remedies for delay

  1. Does the contract provide for the payment of liquidated damages in the event of delay? If so, at what rate and up to what maximum limits? (The level of these damages should impose an adequate incentive on the contractor to complete on time 10-25 per cent. of the contract price as a maximum limit is a reasonable guideline.)
  2. What is “completion” for the purposes of establishing the payment of liquidated damages? Ideally the performance tests should have been successfully completed before completion can take place.
  3. Are there any unusual terms contained in the liquidated damages clause, e.g., liquidated damages calculated as being a percentage of the unfinished part of the work or only payable if the other parts of the project are already in place?
  4. If the contract is governed by English law, does the contract entitle the contractor to claim for extensions of time for employer’s default? (If not, the liquidated damages provision may not be enforceable). What other matters entitle the contractor to claim an extension of time?
  5. Consider the impact of the governing law on liquidated damages.
  6. Does the contract provide for a clear right of the employer to terminate for prolonged delay (i.e., when the maximum limit of liquidated damages has been reached)?
  7. If the employer is entitled to terminate the contract for prolonged delay, what damages are recoverable from the contractor following such termination? Is any element of consequential loss recoverable?
  8. Is there a clause in the contract requiring the contractor to catch up any delay which arises and providing that failure to do so amounts to a breach of the contract?
  9. Is the payment of the contract price front end loaded? The technical adviser should be asked to comment on this. If the contractor receives the bulk of his payment up front, the incentive on him to complete the works may be significantly reduced.

E. Defective work

  1. What is the duty of care imposed by the contract in respect of materials and workmanship?
  2. Does the contract provide for the employer or engineer to be able to inspect the works as they are performed and to require the contractor to put right any defective work?
  3. Is there a defects liability period and, if so, for what period? Does the contract draw any distinction between different aspects of the work (e.g., between engineering and civil works)?
  4. What is the effect of any final certificate issued at the end of the defects liability period? Does the contractor try to exclude his liability in any way for any defects arising after the end of this period (e.g., is there an exclusive remedies clause)?
  5. What does the local law provide as regards a contractor’s residual liability for latent defects?
  6. If the contractor fails to remedy any work for which he is responsible, does the contract entitle the employer to employ a substitute contractor to do this work and then for the employer to recover his costs from the original contractor?
  7. Are there any caps on the liability of the contractor to put right any defective work? Does this cap apply to any re performance requirements imposed on the contractor prior to handover?
  1. What does the contract provide for in respect of defects remedied during the defects liability period, i.e., does a new defects period start to run in respect of the replaced part and/or is the overall defects liability period extended by the period of time during which the works were put out of use due to that particular defect?
  2. How does the contract deal with the responsibility for costs in the situation where the employer requires the contractor to uncover work on the grounds that he has a reasonable suspicion that there may be a defect, having identified a similar defect elsewhere in the works? It is not necessarily logical simply to allocate the costs of uncovering work by reference to whether or not a defect is discovered.
  3. Does the contract require the contractor to notify the employer/engineer prior to any work being covered up?
  4. Is the employer entitled to take over the plant if it is not operating as required by the terms of the contract (e.g., it has failed the performance tests) and recover liquidated damages in respect of the short falls in performance (“buy down” liquidated damages)?
  5. Does the contract exclude liability for consequential and/or economic loss?
  6. Is the employer entitled to deduct sums from interim invoices in respect of defective work?

D. Contract price/payment provisions/tax

  1. Except for clearly identified additional payments, is the contract price a fixed lump sum? Have all entitlements to additional payments been identified in the review?
  2. Is the contract price expressed to include all contingencies and not to be subject to revision to take account of any fluctuations?
  3. How are payments triggered? What is the time for payment? What interest is payable by the employer if there is delay in making payment?
  4. Does the contract provide for payment by reference to milestones? (If so, they should be reviewed by the technical adviser.)
  5. If payment is by milestones, does the contract deal with what is to happen where progress is delayed due to the employer’s default? (The contractor should not be entitled to a milestone payment in these circumstances simply because the employer’s default has prevented this milestone being achieved, since otherwise there is a danger of overpayment.)
  6. Is payment by reference to a pre agreed payment schedule? If so, in what circumstances is the employer entitled to adjust this schedule?
  7. Is the employer entitled to deduct sums for defective work or for the cost of repairs carried out by a replacement contractor?
  8. Does the contract price include any provisional sums? Are these subject to maximum limits?
  9. What is the size of the “project negative” gap throughout the contract, i.e., the gap between expenditure by the employer and value received by the project either in terms of engineering or on the ground? (This should be reviewed by a technical adviser.)
  10. Does the contract envisage amendments to take account of the requirements of export credit agencies?
  11. Does the contract provide for the contractor to supply sufficient evidence of work done with interim invoices in order for the employer to be able to check that payments are due under the contract?
  12. Does the contract provide for any retentions from payments to be made to the contractor?
  13. Is the employer responsible for any taxes otherwise payable by the contractor? If the employer is responsible for payment of such taxes, does the contract expressly exclude penalties payable by the contractor and is there provision for the contractor to reimburse to the employer any tax credits subsequently recovered? (PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008)

References

PPP in Infrastructure Resource Center for Contracts, Laws and Regulations (PPPIRC), 2008. Construction Contract Checklist. [Online]
Available at: http://www.worldbank.org/ppp
[Accessed 25 June 2021].

Victoria, C. A., 2016. Director of Consumer Affairs Victoria. [Online]
Available at: consumer.vic.gov.au/buildingindustry
[Accessed 25 June 2021].

Universal Assignment (December 10, 2023) Module 1 – Project Task 1.3 – Prepare a Contract 2. Retrieved from https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/.
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - December 10, 2023, https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
Universal Assignment June 8, 2022 Module 1 – Project Task 1.3 – Prepare a Contract 2., viewed December 10, 2023,<https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/>
Universal Assignment - Module 1 – Project Task 1.3 – Prepare a Contract 2. [Internet]. [Accessed December 10, 2023]. Available from: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment - Accessed December 10, 2023. https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/
"Module 1 – Project Task 1.3 – Prepare a Contract 2." Universal Assignment [Online]. Available: https://universalassignment.com/module-1-project-task-1-3-prepare-a-contract-2/. [Accessed: December 10, 2023]

Please note along with our service, we will provide you with the following deliverables:

Please do not hesitate to put forward any queries regarding the service provision.

We look forward to having you on board with us.

Categories

Get 90%* Discount on Assignment Help

Most Frequent Questions & Answers

Universal Assignment Services is the best place to get help in your all kind of assignment help. We have 172+ experts available, who can help you to get HD+ grades. We also provide Free Plag report, Free Revisions,Best Price in the industry guaranteed.

We provide all kinds of assignmednt help, Report writing, Essay Writing, Dissertations, Thesis writing, Research Proposal, Research Report, Home work help, Question Answers help, Case studies, mathematical and Statistical tasks, Website development, Android application, Resume/CV writing, SOP(Statement of Purpose) Writing, Blog/Article, Poster making and so on.

We are available round the clock, 24X7, 365 days. You can appach us to our Whatsapp number +1 (613)778 8542 or email to info@universalassignment.com . We provide Free revision policy, if you need and revisions to be done on the task, we will do the same for you as soon as possible.

We provide services mainly to all major institutes and Universities in Australia, Canada, China, Malaysia, India, South Africa, New Zealand, Singapore, the United Arab Emirates, the United Kingdom, and the United States.

We provide lucrative discounts from 28% to 70% as per the wordcount, Technicality, Deadline and the number of your previous assignments done with us.

After your assignment request our team will check and update you the best suitable service for you alongwith the charges for the task. After confirmation and payment team will start the work and provide the task as per the deadline.

Yes, we will provide Plagirism free task and a free turnitin report along with the task without any extra cost.

No, if the main requirement is same, you don’t have to pay any additional amount. But it there is a additional requirement, then you have to pay the balance amount in order to get the revised solution.

The Fees are as minimum as $10 per page(1 page=250 words) and in case of a big task, we provide huge discounts.

We accept all the major Credit and Debit Cards for the payment. We do accept Paypal also.

Popular Assignments

5 Places you must visit in Busan, South Korea

Write 2 articles 1st Topic: 5 Places you must visit in Busan, South Korea 2nd topic: Korean language: various tips and resources to learn Deadline: 10th October 2023 12:00 AM Instructions: Article Structure is given below Meta Description: First, you will start with a meta description of your article in

Read More »

2002HSV Human Services Research

Assessment 2: Written research proposal Worth 45% of final grade Complete your answers in this assignment template Name: xxxxxxx Student ID: xxxxxxx Title: xxxxxxx Exact word count (exc. cover sheets and reference list; max. 2,000 words): x,xxx Please specify the research methodology are you proposing to use: ☐ Quantitative                                    ☐

Read More »

COIT29226 Introduction to IoT

Assessment item 3 – Project Due date: Week 12 (8 October 2023) 11:55 pm AEST Weighting: Length: Submission: 50% There is no word limit for this report Group work (submit via Moodle) Objectives This assessment item relates to the following unit learning outcomes: Learning Outcomes Assessed: Enabling objectives What do

Read More »

BUSM1008 Assessment 2 Brief Spring 2023

Assessment 2: Individual Report (20%) and Presentation (20%) Background You are appointed as a business consultant, recruited by the company allocated to you in week 6 by your tutor.  Your role is to undertake research on the company, the allocated topic and an issue identified in the media in relation to your company and

Read More »

ECON1020 PRINCIPLES OF ECONOMICS

INDIVIDUAL ASSIGNMENT Total Marks 100 | Weighting 25% DUE: 29/09/2023, 11:55pm IMPORTANT INFORMATION: READ BEFORE YOU START SUBMISSION 11.55 pm. A 1-hour grace period is provided to students who experience a technical concern. DOCUMENT PREPARATION REFERENCING UNACCEPTABLE ACADEMIC ACTIVITIES MARKING Question 1 | [12 marks] Download the spreadsheet data that

Read More »

ENTERPRISE LAW LAWS1001

Assessment task 3 Individual Case Study This task is the result of your individual effort, so students must not discuss their work with anyone else, otherwise it may lead to an allegation of collusion. Weight: 15% Due: Before 5 pm on Wednesday 27th September. Late submissions will incur a penalty

Read More »

International Business INBU01-7

Module International Business INBU01-7 (NQF LEVEL 7) FORMATIVE ASSESSMENT – ASSIGNMENT C Assignment C (INBU01-7/DLO4 10/2023) Exam Date 20 October 2023 Marks 50 Assignment C (INBU01-7/DLO4 10/2023)   Total: 20 marks SECTION A (10 MARKS) – PARAGRAPH QUESTION Question 1 (10 marks) Coca-Cola is marking its 70th year in Nigeria

Read More »

Summative Assessment Help

Summative Assessment Brief: Learning Outcomes: LO1: Construct a problem/issue/need identified from practice that impacts on individual outcomes LO2: Formulate a focus-based enquiry on the identified problem/issue/need utilising an area of individual learner interest LO3: Critically evaluate the evidence base to support the proposal of the solution focused initiative LO4: Develop

Read More »

EDU30067 Teaching English

Assignment 2: Folio Template INTRODUCTION:         LESSON 1 Lesson title:   Year level: Topic:   Duration of lesson: Curriculum links: Strands & sub-strands Content descriptions       Students background knowledge: What is your starting point – what do the students already know, what have they done

Read More »

Edge Computing Security and Privacy

Proposal Background Title: Edge Computing Security and Privacy Proposal The new computing paradigm in the Internet of Things domain is known as IoT edge computing which functions by processing calculations at the edge of the network (Alli & Alam, 2020). The current technology aided by cloud and fog computing has created

Read More »

Foundations of Communication Assessment 2 Instructions

Discussion task (Total grade – 10%)   Process Work (Steps to complete the task) Answer on the Assessment 2 Submission Document – Do not upload this instruction document. Requirements (important elements to include) lastname_firstname_studentID_COMS_Assess 2_semester_year. Process for Assessment discussion tasks NOTE: If you do not participate in the class discussions then

Read More »

Assessment Two Dos and Don’ts (Internal)

Do: Read the assessment instructions carefully Read the marking rubric carefully Understand the question – break it down Conduct research – record the reference details Read the topic materials about communication theories, forms and factors and refer to them Contribute to the discussions in class or no marks for the

Read More »

Unpacking the Question: Assessment Two

Studying at university requires you to become familiar with strategies to un-pack or breakdown a variety of assessment questions/tasks throughout your studies.  Task Example of integrating the discussion, research and theories. In the group discussion my group members (name them) stated that an advertisement for a beauty product would most

Read More »

MGMT0001 Introduction to Commerce Assessment

MGMT0001 Introduction to Commerce Assessment 2 (worth 30%) Due date:                  2:00pm (AWST) Friday 15th September 2023 Submission:              Via Turnitin assessment submission link (see ‘Assessment 2’ folder in ‘Assessments’ section of Blackboard). Additional Instructions: Part A (42 marks) Nathan is a well-known chef with years of experience cooking various cuisines. After

Read More »

ACCT5011: Accounting Systems in the Digital Age

Practical Assignment Guide, Semester 2, 2023 Due Date for Submission: Monday 11th September 2023 at 5.00 PM Please note that the Folio Assignment for ACCT5011 Accounting Systems in the Digital Age is an individual assessment task worth 30% of your total marks in the unit. Please refer to the online

Read More »

EC229- Review session

Assume two cities, A and B, that can’t trade between them. Each city produces its own coconuts for its local market. If suddenly trade is possible then: D) As we saw in class, the new price will be somewhere between the original price 𝑃_𝐴,𝑃_𝐵. Hence it is impossible for consumers

Read More »

Computing Theory COSC

Computing Theory COSC 1107/1105 Assignment 1: Fundamentals Assessment Type Individual assignment. Submit online via Canvas → As- signments → Assignment 1. Marks awarded for meeting re- quirements as closely as possible. Clarifications/updates may be made via announcements/relevant discussion forums. Due Date Week 6, Sunday 27th August 2023, 11:59pm Marks 125

Read More »

BE279 Applied Statistics and Forecasting

Strategy, Operations, & Entrepreneurship Group Essex Business School Module Code BE279 Module Title Applied Statistics and Forecasting Assessment Type Individual Report (2,000 word) Academic Year 2022/23, Spring Term Submission Deadline Refer to FASER Task Specific Guidance Please note that: Module Learning Outcomes On successful completion of the module, students will

Read More »

Learning Design Tool: Little Learners Level 1 sounds

Learning Design Tool: Little Learners Level 1 sounds. Prepared by Sara Hart Date 30th August, 2023 (feel free to leave this date as it is the AT2 due date) Brief description of Learning Design   Chooseit Maker: Create, edit and play personalised learning activities that can be used in your

Read More »

HUMN1041 PEOPLE, PLACE AND SOCIAL DIFFERENCE ASSIGNMENT

HUMN1041 PEOPLE, PLACE AND SOCIAL DIFFERENCE ASSIGNMENT 1 TEMPLATE This assignment is made up of three (3) parts, plus a reference list and appendix. Marks are allocated for each section, as follows: – 1 mark Please ensure that you provide your answers in this template, and provide a Reference list

Read More »

Model 3 Launch in Australia

Client Information Company Name Tesla Contact Name   Email   Phone Number   Address Level 14, 15 Blue St. North Sydney, NSW 2060 Australia Ad link & image Project Information Project Title Model 3 Launch in Australia Project Description (100 words) Highlight the uniqueness of the car. Show the superior

Read More »

MKT10009 Marketing and the Consumer Experience

School of Business, Law and Entrepreneurship Assessment Task – Assignment 2  MKT10009 Marketing and the Consumer Experience Semester 2, 2023. Assessment Type Analytical Report Associated Unit Learning Outcomes (ULO’s) 2, 3, 4 Group or Individual task Individual Value (%) 25% Due Date Monday 20th September at 10:00 AET – Enterthis

Read More »

ASSIGNMENT – 1st Evaluation

ASSIGNMENT – 1st Evaluation Date of Submission- 4TH SEP 2023 25 MARKS COMPARATIVE PUBLIC LAW Q. You are the new Central Minister for Urban Development who is keen to make major Indian cities as smart cities. You visit different countries like USA, UK, European Countries, Japan and other developed countries

Read More »

Corporate & Financial Due Diligence Report

[Name of the company] Note: Students should keep in mind that application of legal provisions (including Securities Regulations) and analysis of the same is important. Merely putting the facts and figures won’t fetch even a decent mark. Note: Students should only mention the broad area of business. This part should

Read More »

ECON1000 S2 2023 – Marking Guidance and FAQs on GTP

Students will be marked on the extent to which they specifically answer the question and provide clear, logical, well-reasoned and sufficient explanations. Here is a summary breakdown of how marks are allocated in this GTP: Part 1 [15 marks] §  Providing relevant observations from the information provided in the articles

Read More »

ECON1000 S2 2023 – GTP Brief

ECON1000 S2 2023 – GTP Brief A.  Context and Overview The Game Theory Presentation (GTP) is worth 30% of the final mark. GTP is a ‘take-home’ exercise with a set of tasks to do. The GTP is based on Lecture Topics: L1 and L2. You will have twenty (21) days

Read More »

Order #35042 Human Rights Research Essay

Draft due 26th Aug 2,500 words (excluding references and bibliography) Instructions: Structure: Title – The Tigray War: A Critical Analysis of What the Future Holds for Human Rights in the Region What can be done to ensure human rights violations will cease and be prosecuted? Expand on different actors and

Read More »

PMC1000: Applied Pathology

Assessment Task Sheet: Poster Presentation Date: Thursday 31st August 2023 | Weighting: 30% Assessment Task 2 You are required to develop a handout style resource (pamphlet or brochure) on a selected pathological condition which is aimed at first year student paramedics. You will need to use high quality peer reviewed

Read More »

Detailed Information: Reflective Assignment

Indigenous Peoples, Law and Justice Detailed Information: Reflective Assignment Due Date:                   Tuesday 5th September 2023 at 4:00 pm (AWST). Marks:                       30% of the total marks for this unit. Assignment:              The assignment will comprise two questions. Students must answer all parts of both questions. Examinable topics: The cultural immersion exercise and/or

Read More »

Can't Find Your Assignment?

Open chat
1
Free Assistance
Universal Assignment
Hello 👋
How can we help you?